Difference between revisions of "Run Planning Meeting Notes, December 7 - December 14, 2022"

From GlueXWiki
Jump to: navigation, search
(Short term run plan)
Line 41: Line 41:
  
 
=== Short term run plan ===
 
=== Short term run plan ===
*TAC run?
+
*TAC run? (may be on weekend)
 
*Take date on LHe FULL target at 200nA beam
 
*Take date on LHe FULL target at 200nA beam

Revision as of 10:09, 8 December 2022

Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Hall D Logbook


Thursday Dec. 8th

Last 24h

  • Wednesday was RF recovery day, Hall was in Controlled Access till ~6:30pm, many things where done during access in Hall.
    • Hall (Controlled Access):
      • Tim worked on Tagger magnet NMR [1]
      • Sasha replaced the BCAL fADC [2]
      • DIRC checkout (Justin+1).
      • Sasha, Vlad, Lubomir, Sergei and Arshak: work in the PS test area.
      • Sasha, Arshak and Malte did some preliminary noise level tests at FCAL
      • Mark Stevens: walkthrough for OPS.
      • Tim and Eugene checked the man-lift
      • Tim and Sasha checked by how much FCal can be pushed back (for some tentative PrimEx systematic measurements).
  • After beam comes back:

Shift Summaries

Issues

Short term run plan

  • TAC run? (may be on weekend)
  • Take date on LHe FULL target at 200nA beam