(Thursday, Dec 5 at 08:45)
Line 16: Line 16:
 
#* Sean got the general detector checkout done.   
 
#* Sean got the general detector checkout done.   
 
#* Sasha did the PS threshold scan and set up the PS trigger for Richard's uscope scan  
 
#* Sasha did the PS threshold scan and set up the PS trigger for Richard's uscope scan  
#* Richard's uscope scans half done, interrupted by fake PSS button press from tagger hall  
+
#* Sasha set up trigger config for straight tracks w GEM, excluding uscope so Richard can work independently
#* Sasha setting up trigger config for straight tracks w GEM
+
#* Richard's uscope scans half done, interrupted by ghost PSS button press from tagger hall, no beam from approx 9pm - 1am?
#* MCC to start setting up hall A for RF stress testing tomorrow so trips expected during swing and owl
+
#* [https://logbooks.jlab.org/entry/3746870 Lubomir's logentry] 
 
#Issues
 
#Issues
 
#* Solenoid alarm
 
#* Solenoid alarm
 
#* PSS fault
 
#* PSS fault
# Plan for today
+
#* GEM cable or module swap
#* Hope to collect enough straight tracks in GEM position 1 to move to 2 when Justin gives the okay, possibly at 6am
+
# Plan for today  
#* Move GEM to position 2, then take more data until ~4pm?
+
#* After the meeting (TBD Justin), move GEM to position 2, fix electronics problem, then take more data until ~4pm?
 
#* Move GEM to position 3, then take more data until ~6am Friday?  
 
#* Move GEM to position 3, then take more data until ~6am Friday?  
 
# Plan for later  
 
# Plan for later  
 
#*  [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Fall2019_Run#Runplan Alexandre's comprehensive runplan] now at 3-4
 
#*  [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Fall2019_Run#Runplan Alexandre's comprehensive runplan] now at 3-4
 
#Notes from this meeting.
 
#Notes from this meeting.

Revision as of 07:34, 5 December 2019

<- Back to Run Coordination Meetings:Fall2019 Run

Thursday, Dec 5 at 08:45

  1. Last 24h:
    • Straight tracks during the day, Justin & Sean working to debug recon and analyze the data
    • Sean got the general detector checkout done.
    • Sasha did the PS threshold scan and set up the PS trigger for Richard's uscope scan
    • Sasha set up trigger config for straight tracks w GEM, excluding uscope so Richard can work independently
    • Richard's uscope scans half done, interrupted by ghost PSS button press from tagger hall, no beam from approx 9pm - 1am?
    • Lubomir's logentry
  2. Issues
    • Solenoid alarm
    • PSS fault
    • GEM cable or module swap
  3. Plan for today
    • After the meeting (TBD Justin), move GEM to position 2, fix electronics problem, then take more data until ~4pm?
    • Move GEM to position 3, then take more data until ~6am Friday?
  4. Plan for later
  5. Notes from this meeting.