Difference between revisions of "Run Planning Meeting Notes, Apr 26-May 2, 2018"

From GlueXWiki
Jump to: navigation, search
m
Line 25: Line 25:
 
#**Production Running
 
#**Production Running
 
#*Longer term run plan/Other items
 
#*Longer term run plan/Other items
#**[https://halldweb.jlab.org/wiki/images/5/5f/Spring18_week16.jpg]
+
#**Access to remove plate from beam profiler
 
#*End of run preparation
 
#*End of run preparation
 
#**Be prepared to switch everything off after last beam at 6 am, SUNDAY May 6
 
#**Be prepared to switch everything off after last beam at 6 am, SUNDAY May 6

Revision as of 19:52, 1 May 2018

<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run

Wednesday, May 2 at 08:45

  1. Notes from previous 24 hours:
    • Production running
    • Raster scan now working
    • MCC harp scans seem to be fine
  2. Issues:
  3. Reports:
  4. Run Plan
    • Wednesday
      • RF recovery
      • 12 GeV Inauguration(!) Tour
      • Access to uninstall muon chamber
      • Raster Scan(?)
    • Thursday
      • Raster Scan(?)
      • TAC Run
    • Friday
      • Production Running
    • Longer term run plan/Other items
      • Access to remove plate from beam profiler
    • End of run preparation
      • Be prepared to switch everything off after last beam at 6 am, SUNDAY May 6
      • Shutdown list
  5. AOB


Tuesday, May 1 at 08:45

  1. Notes from previous 24 hours:
    • Accesses during beam studies
    • Resuming production running
    • MCC harp scans should be in tune mode
  2. Issues:
    • High-Level Monitoring [4]
    • Occupancies in tagger monitoring [5]
  3. Reports:
  4. Run Plan
    • Tuesday
      • Production Running
      • Raster Scan Studies
    • Wednesday
      • RF recovery
      • 12 GeV Inauguration(!) Tour
      • Access to uninstall muon chamber
    • Thursday
      • TAC Run
    • Longer term run plan/Other items
    • End of run preparation
      • Be prepared to switch everything off after last beam at 6 am, SUNDAY May 6
      • Shutdown list
  5. AOB

Monday, April 30 at 08:45

  1. Notes from the weekend:
    • Production running
    • Vertical beam position [7][8][9]
    • Monitoring Plots [10]
  2. Issues:
    • TOF voltage failure [11]
    • Gluon49 failure
    • Open Door
  3. Reports:
  4. Run Plan
    • Monday
      • Beam studies
      • Accesses
        • TOF
        • FCal
        • Muon Chamber
    • Tuesday
      • RF recovery (moved to Wednesday)
    • Wednesday
      • 12 GeV Inauguration(!) Tour
      • TAC Run (Move to Thursday?)
    • Longer term run plan/Other items
      • Resumption of raster scan studies
    • End of run preparation
      • Be prepared to switch everything off after last beam at 6 am, SUNDAY May 6
  5. AOB

Sunday, April 29 - No Meeting

Saturday, April 28 - No Meeting

Friday, April 27 at 08:45

  1. Notes from the previous 24 hours:
  2. Issues:
    • Rootspy crashes and recovery [22][23]
    • Time differences in monitoring plots [24]
  3. Reports:
  4. Run Plan
    • Friday
      • High rate DAQ tests (9.30 am)
      • Injector recovery (MCC, possible beam down ~1hr)
      • Level 1 trigger studies
    • Saturday
      • Production Running
    • Sunday
      • Production Running
    • Longer term run plan/Other items
      • Resumption of raster scan studies
      • Access for Muon detector
      • Tour
      • TAC Run (Wednesday)
    • End of run preparation
      • Be prepared to switch everything off after last beam at 6 am, SUNDAY May 6
  5. AOB

Thursday, April 26 at 08:45

  1. Notes from the previous 24 hours:
    • Replacement of TAGH FDC module [27]
    • Production running
    • High rate trigger tests
  2. Issues:
    • Resuming DAQ after Wednesday tour [28]
    • Running with 750 um converter
    • Hot Channels, delta t offsets [29]
  3. Reports:
  4. Run Plan
    • Thursday
      • Level 1 trigger test
      • High rate trigger test part II(?)
      • Low current BPM lock test (afternoon)
    • Friday
      • High rate DAQ tests (9.30 am)
      • TAC Run (2 pm)
    • Saturday
    • Longer term run plan
  5. AOB