Difference between revisions of "Run Planning Meeting Notes, Apr12-Apr 18, 2018"

From GlueXWiki
Jump to: navigation, search
(Monday, April 16 at 08:45)
(Monday, April 16 at 08:45)
Line 86: Line 86:
 
#* Production this evening
 
#* Production this evening
 
#* RF recovery tomorrow
 
#* RF recovery tomorrow
 +
#* Best time to try to try the low current lock on the AC for the next TAC run? Tentatively postponed until Wed. before raster tests
 
#** Switch AC to 3.5 mm collimator
 
#** Switch AC to 3.5 mm collimator
#*** Take data through Thurs. with this setting
+
#*** Take data through Thurs. with this setting: 150 nA, 75 micron converter, 0/90, AMO
 +
 
 
# AOB
 
# AOB
  

Revision as of 08:32, 16 April 2018

<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run

Thursday, April 12 at 08:45

  1. Notes from the previous 24 hours:
    • TAC run (evening strip chart) was finished around 10pm. Took data with both the 750um and 75um converter.
    • Production started around 11 pm and has continued through the night.
  2. Issues:
    • When adjusting a procedure, please contact the expert before doing so to make sure the changes you make are okay.
    • ~1hr 20 mins of DAQ issues while the target was filling and we could not run in raw mode.
    • PS scalers (Alexandre)
  1. Reports:
  2. Run Plan
    • Pass change this morning
      • Short access to install copper and tungsten shields
      • Move muon chamber back into beam line
    • Production running
      • Harp scan when beam comes back
    • Fast raster scan postponed to Monday
    • Any more systematic studies we want to do?
  3. AOB

Friday, April 13 at 08:45

  1. Notes from the previous 24 hours:
  2. Issues:
    • Bill noticed some minor inconsistencies with monitoring plots (beta vs. p, beam energy, and trigger bit)
  3. Reports:
  4. Run Plan
  1. AOB
    • Have Lubomir for opportunistic access to remove Cu and half of W shield- any others? Beam studies on Monday and RF recovery Tuesday
    • Run meeting this weekend?

Saturday, April 14 at 08:45

No meeting

Sunday, April 15 at 08:45

No meeting

Monday, April 16 at 08:45

  1. Notes from the previous 48 hours:
  1. Issues:
  2. Reports
  3. Run Plan
    • 8hr beam studies today
      • Controlled access to adjust shielding, replace AC voltage adapter, FCAL bases, and other technician work
    • Finish materials scan
    • Production this evening
    • RF recovery tomorrow
    • Best time to try to try the low current lock on the AC for the next TAC run? Tentatively postponed until Wed. before raster tests
      • Switch AC to 3.5 mm collimator
        • Take data through Thurs. with this setting: 150 nA, 75 micron converter, 0/90, AMO
  1. AOB

Tuesday, April 17 at 08:45

Wednesday, April 18 at 08:45