Monday, November 7

Past 72 hours

  • Friday. We took production data in empty target all day until Saturday morning
  • Saturday Day: Total accumulated events for the empty target ~2.5B
  • Started running Empty target production whenever we had beam. (No beam for ~4.5 hours for a NL access)

Shift Summary

Issues/Reports

Cycling TAG5C (Daniel Moser)
Hard reboot worked (Arshak)

Plan

  • Continue with empty target production.
  • (Note): Hall B plans to change to a 1/2 wave plate at some point Today.
  • After empty production completed: calibration of CompCal modules with adjusted HV, 1 hr at low intensity (Sasha)

Friday, November 4

Past 24 hours

  • Emptied the target at 9 am. No problems on that
  • Started running Empty target production whenever we had beam. (No beam for ~4.5 hours for a NL access)

Shift Summary

Issues/Reports

Cycling TAG5C (Daniel Moser)
Hard reboot worked (Arshak)

Plan

  • Continue with empty target production.
  • (Note): Hall B plans to change to a 1/2 wave plate at some point Today.
  • After empty production completed: calibration of CompCal modules with adjusted HV, 1 hr at low intensity (Sasha)

Thursday, November 3

Past 24 hours

  • Maintenance day. Got Beam Back in the Swing shift.
  • Harp scans after beam returned. [1] [2]
  • Full target production all night whenever we had beam.
  • Beam has been unstable. Related to issue to reduce HALO counts above 4nA for Hall B.

Shift Summary

Issues/Reports

Plan

  • 9:30 am Empty target, then start production
  • After empty production completed: calibration of CompCal modules with adjusted HV, 1 hr at low intensity (Sasha)