RC summary, 09/17/2020 - 09/21/2020, Igal Jaegle

Dung the last 6 days of the beam, we took production data and carried out two tests: PS ans CCAL.

  1. Physics production: total 18.06B - perp 8.18B para 7.86B amo 2.02B