RC summary, 08/27/2020 - 09/02/2020, Igal Jaegle

During the first 4 days, we were in data production more and for the last 3 days were devoted to CPP tests & DIRC commissioning. The downtime due to us was large: 38.8hr

    • 12hr hall access for installing the CPP test
    • 14hr hall access for de-installing the CPP test and installing TRD-GEM
    • 12.8hr invasive hall access for detector (DIRC) repair, active collimator scan, changing radiator, and starting runs