*DIRC problems (South Box Group 9 LV) which required invasive hall access
 
*DIRC problems (South Box Group 9 LV) which required invasive hall access
 
*Solenoid did not ramp down and up as expected delaying the TRD-GEM installation by 5 hours
 
*Solenoid did not ramp down and up as expected delaying the TRD-GEM installation by 5 hours
*Beam down due to weather conditions & Hall C 1 pass changed
+
*Beam down due to weather + communication wrath during 18hr
 
Apart from that, in total 18B "good" physics trigger were taken.
 
Apart from that, in total 18B "good" physics trigger were taken.

Latest revision as of 20:22, 12 September 2020

RC summary, 08/27/2020 - 09/02/2020, Igal Jaegle

During the first 4 days, we were in data production more, and the last 3 days were devoted to CPP tests & DIRC commissioning. The downtime due to us was large: 38.8hr

  • 12hr hall access for installing the CPP test
  • 14hr hall access for de-installing the CPP test and installing TRD-GEM
  • 12.8hr invasive hall access for detector (DIRC) repair, active collimator scan, changing radiator, and starting runs

The most notable issues were

  • CDC & FDC HV did trip without any alarms resulting in the loss of 3 data production runs
  • DIRC problems (South Box Group 9 LV) which required invasive hall access
  • Solenoid did not ramp down and up as expected delaying the TRD-GEM installation by 5 hours
  • Beam down due to weather + communication wrath during 18hr

Apart from that, in total 18B "good" physics trigger were taken.