Online task list for 2011

From GlueXWiki
Revision as of 15:46, 18 March 2011 by Davidl (Talk | contribs)

Jump to: navigation, search

The table below contains activities from the 12GeV project schedule in the Online Computing section which have work scheduled for FY2011. Detailed descriptions for the activities are kept at the bottom of the page and can be jumped to by clicking the short description in the table.

A breakdown of each activity into smaller tasks is maintained in an Excel file on the group disk here:


/group/halld/Individual-Schedules/Online_Computing




Activity Line Activity Name Man-weeks Names of people Comments
1532025 Plan Front End Software 16.5 D. Lawrence, D. Abbott, B. Moffit
1532030 Plan DAQ Software Event Unblocking 9 D. Lawrence, D. Abbott, B. Moffit
1532030a Plan DAQ Software Scripts 6
1532030b Plan DAQ Run Control 5  ? + V. Gyurjyan Mostly Vardan
1532030c Plan DAQ Code Management 4
1532035 Plan Monitoring Framework 6  ? + V. Gyurjyan
1532035a Plan Monitoring Scalers 3
1532035b Plan Monitoring Histograms 4 D. Lawrence
1532035c Plan Remote Monitoring 3  ? + V. Gyurjyan
1532035d Plan Monitoring Hardware 4  ? + V. Gyurjyan
1532035f Plan Monitoring Processes 3  ? + V. Gyurjyan
1532035g Plan Monitoring Trigger 2 S. Somov + V. Gyurjyan
1532040 Plan Alarm Systems 6 Universities are expected to contribute more
1532045 Plan Archiving DAQ Configuration 3
1532045a Plan Archiving Run Info 5
1532045b Plan Archiving Controls 5
1532050 Plan Event Display 2 Universities are expected to contribute more
1532055 Plan Storage Management 11.3 Computer Center can help
1532060 Plan Controls Framework 4  ? + V. Gyurjyan
1532060a Plan Display Management 3
1532060b Plan Controls Backup/Restore 3
1532060c Plan Controls Magnet PS 4
1532060d Plan Controls HV 3
1532060f Plan Controls LV 4
1532060g Plan Controls Motors 4
1532060h Plan Controls Gas Systems 4
1532060j Plan Controls Temperature 4
1532060k Plan Controls Target 5
1532060n Plan Controls/DAQ interface 3  ? + V. Gyurjyan Mostly Vardan
1532065 Trigger Board Initialization 27 S. Somov + Electronics Group Two-year duration
1532035 Level 1 Verification 24 S. Somov + Electronics Group Two-year+ duration