==Open Action Items==
 
==Open Action Items==
  
* Form group to revisit energy-sum trigger algorithm - Alex S, Dave D, Elliott, and new Chinese group - 29-Nov-2007
 
 
* Determine requirements for and set up CODA-based Electronics group test stands - Elliott W, Chris C, Dave A, 9-Aug-2007
 
* Determine requirements for and set up CODA-based Electronics group test stands - Elliott W, Chris C, Dave A, 9-Aug-2007
  
Line 7: Line 6:
 
==Action Items In Progress - Short Term==
 
==Action Items In Progress - Short Term==
  
 +
* Revisit energy-sum trigger algorithm - Alex S (+ Dave D, Elliott) - 29-Nov-2007
 
* Use full-scale FDC test as testbed for controls system - Elliott, 31-Jan-2008
 
* Use full-scale FDC test as testbed for controls system - Elliott, 31-Jan-2008
 
** Developing initial test system in DAQ lab instead- Elliott, Vardan, Feb 2008
 
** Developing initial test system in DAQ lab instead- Elliott, Vardan, Feb 2008
* Add electronics design goals and milestones to online design goals and milestones wiki pages - Fernando, 15-Dec-2007
 
 
* Determine expected average event size - Alex, Eugene, Elliott, David, Fernando, Nov-2007
 
* Determine expected average event size - Alex, Eugene, Elliott, David, Fernando, Nov-2007
  
Line 26: Line 25:
 
==Completed Action Items==
 
==Completed Action Items==
  
 +
* Add electronics design goals and milestones to wiki pages - Fernando, 15-Dec-2007 - completed Mar-2008
 
* Complete Monitoring/Controls milestones - Elliott, 19-Jul-2007, completed Feb 2008
 
* Complete Monitoring/Controls milestones - Elliott, 19-Jul-2007, completed Feb 2008
 
* Generate information for Elke's Action Item Tracker based on Online Major Milestones - Elliott, 15-Dec-2007, completed Jan-2008
 
* Generate information for Elke's Action Item Tracker based on Online Major Milestones - Elliott, 15-Dec-2007, completed Jan-2008

Revision as of 15:37, 10 April 2008

Open Action Items

  • Determine requirements for and set up CODA-based Electronics group test stands - Elliott W, Chris C, Dave A, 9-Aug-2007


Action Items In Progress - Short Term

  • Revisit energy-sum trigger algorithm - Alex S (+ Dave D, Elliott) - 29-Nov-2007
  • Use full-scale FDC test as testbed for controls system - Elliott, 31-Jan-2008
    • Developing initial test system in DAQ lab instead- Elliott, Vardan, Feb 2008
  • Determine expected average event size - Alex, Eugene, Elliott, David, Fernando, Nov-2007


Action Items In Progress - Longer Term

  • Complete Trigger/DAQ/Monitoring/Controls work breakdown - Elliott, 9-Aug-2007


Action Items on Hold

  • Form FCAL test subgroup and plan 2008 FCAL test - Elliott, 4-Oct-2007
    • Not clear if and when test will happen given new accelerator schedule - Elliott, 16-Jan-2008


Completed Action Items

  • Add electronics design goals and milestones to wiki pages - Fernando, 15-Dec-2007 - completed Mar-2008
  • Complete Monitoring/Controls milestones - Elliott, 19-Jul-2007, completed Feb 2008
  • Generate information for Elke's Action Item Tracker based on Online Major Milestones - Elliott, 15-Dec-2007, completed Jan-2008
  • Derive manpower requirements from Trigger/DAQ milestones - Elliott and Graham, 15-Dec-2007, completed by Elke Dec-2007
  • Design document listing basic requirements and design goals - Elliott, 19-Jul-2007, completed 15-Dec-2007
  • Combine and reconcile DAQ and Hall D milestones - Elliott and Graham, 29-Nov-2007, completed 15-Dec-2007
  • Milestones from JLab DAQ group - Graham H, 19-Jul-2007, completed 29-Nov-2007
  • DAQ board specifications needed by Electronics group - Dave A, 9-Aug-2007, completed 15-Oct-2007
  • Form committee to lead effort to determine event size - Elliott, 29-Aug-2007, completed 20-Sep-2007
  • Trigger/DAQ milestones - Elliott, 19-Jul-2007, completed 15-Aug-2007
  • Create task-oriented list of OWG responsibilites instead of existing group-oriented list - Elliott, 15-Jun-07, superceded 9-Aug-2007
    • Instead, create work breakdown in Contractor - 9-Aug-2007
  • Replace "GlueX" with "Hall D" in wiki pages - Elliott, 15-Jun-07, completed 20-Jun-07