Line 3: Line 3:
 
* Announcements
 
* Announcements
 
* Review of minutes from [[OWG meeting 22-Aug-2008 | 22-Aug-2008]] meeting
 
* Review of minutes from [[OWG meeting 22-Aug-2008 | 22-Aug-2008]] meeting
 +
* [[Media:Online-Graham-5-Sep-2008.ppt|DAQ update]] - Graham
 
* Collaboration meeting - [http://www.jlab.org/Hall-D/software/wiki/index.php/GlueX-Collaboration-Sept-2008 agenda], preparation - All
 
* Collaboration meeting - [http://www.jlab.org/Hall-D/software/wiki/index.php/GlueX-Collaboration-Sept-2008 agenda], preparation - All
 
* Update on fiber test stand - Beni
 
* Update on fiber test stand - Beni
* DAQ update - Graham
+
* Trigger hardware development - Dave D, Fernando, or Chris
 
* Electronics update - Fernando, Chris, Ben, Ed, etc.
 
* Electronics update - Fernando, Chris, Ben, Ed, etc.
* Trigger update - Alex
 
  
  
Line 23: Line 23:
 
'''No meeting 19-Sep-2008 due to GlueX Collaboration meeting'''
 
'''No meeting 19-Sep-2008 due to GlueX Collaboration meeting'''
  
Tentative:  3-Oct-2008 2pm CC F326
+
Fri 3-Oct-2008 2pm CC F326
  
  
Line 30: Line 30:
  
 
=Minutes=
 
=Minutes=
 +
 +
Attendees:  Elliott W, Graham H, Simon T, Dave D, Elton S, David L, Mark I, Alex S, Dave A, Carl T, Vardan G, Beni Z, Jim S.
 +
 +
 +
'''DAQ Status'''
 +
 +
Graham gave an overview of recent progress in the DAQ group.  See his talk for numerous details.
 +
 +
* EMU prototype done, now being tested.
 +
* Uses Java and C (native methods).
 +
* EMU<->EMU communications tested, easily saturates GB Ethernet bandwidth with low CPU usage.
 +
* Estimate need seven DAQ staff members to complete CODA3, have five now.  Two more approved but not funded.
 +
* Completion dates will slip if staff members not hired.
 +
 +
 +
'''Collaboration Meeting Agenda'''
 +
 +
Agenda include talks on electronics by Fernando, trigger by Dave D, and DAQ/controls by Elliott (given by Dave L, as Elliott will be out of town).
 +
 +
 +
'''Fiber Test Stand'''
 +
 +
Beni reported he is taking data with no problems.  Dark box materials still have not arrived.  It takes 5-6 hours to test one fiber.
 +
 +
 +
'''Trigger Status'''
 +
 +
Dave D noted that the CTP and SD are coming along, the TI prototype is working.  Expect contracts for boards by the end of FY 08.
 +
 +
 +
'''Electronics'''
 +
 +
Dave A reported:
 +
 +
* Mini-SD board coming, uses front panel connectors.
 +
* PCI-based TI prototype working at basic level, more testing and development needed.

Latest revision as of 14:07, 10 September 2008

Agenda

  • Announcements
  • Review of minutes from 22-Aug-2008 meeting
  • DAQ update - Graham
  • Collaboration meeting - agenda, preparation - All
  • Update on fiber test stand - Beni
  • Trigger hardware development - Dave D, Fernando, or Chris
  • Electronics update - Fernando, Chris, Ben, Ed, etc.


Time/Location

5-Sep-2008 2pm CC F326


Announcements

Next Meeting

No meeting 19-Sep-2008 due to GlueX Collaboration meeting

Fri 3-Oct-2008 2pm CC F326


New Action Items from this Meeting

Minutes

Attendees: Elliott W, Graham H, Simon T, Dave D, Elton S, David L, Mark I, Alex S, Dave A, Carl T, Vardan G, Beni Z, Jim S.


DAQ Status

Graham gave an overview of recent progress in the DAQ group. See his talk for numerous details.

  • EMU prototype done, now being tested.
  • Uses Java and C (native methods).
  • EMU<->EMU communications tested, easily saturates GB Ethernet bandwidth with low CPU usage.
  • Estimate need seven DAQ staff members to complete CODA3, have five now. Two more approved but not funded.
  • Completion dates will slip if staff members not hired.


Collaboration Meeting Agenda

Agenda include talks on electronics by Fernando, trigger by Dave D, and DAQ/controls by Elliott (given by Dave L, as Elliott will be out of town).


Fiber Test Stand

Beni reported he is taking data with no problems. Dark box materials still have not arrived. It takes 5-6 hours to test one fiber.


Trigger Status

Dave D noted that the CTP and SD are coming along, the TI prototype is working. Expect contracts for boards by the end of FY 08.


Electronics

Dave A reported:

  • Mini-SD board coming, uses front panel connectors.
  • PCI-based TI prototype working at basic level, more testing and development needed.