Line 30: Line 30:
 
     can be done by the end of the year.
 
     can be done by the end of the year.
 
   - DSC suggested to proceed with sandwich construction using kapton
 
   - DSC suggested to proceed with sandwich construction using kapton
     blanks.  We will wnt to see how quickly the sandwich can be
+
     blanks.  We will want to see how quickly the sandwich can be
 
     put together.
 
     put together.
 
   - Dummy flex board design was completed by Jeff Wilson last week.
 
   - Dummy flex board design was completed by Jeff Wilson last week.

Revision as of 16:57, 3 April 2007

FDC Weekly Meeting

Date: November 8, 2006

Participants: Daniel, Brian, Simon, Chuck, Tim

Next Meeting: Wednesday, November 15, 2006 @ 1:30 p.m.


1). Mechanical Drawings:

   Chuck and Tim presented first mechanical drawings of the FDC.
   We went over what they did and made suggestions.
 - We need to redo the preamp daughter board placement.
    > 6 daughter boards per anode board (96 wires).
    > 12 daughter boards per cathode board (192 cathodes).
    > All daughter boards must be located with 120 deg arc.
 - Work to reduce the number of bolt holes - need to set spacing
   to be compatible with all +/-45 deg, +/-60 deg configurations.
 - Design sealing cams for chamber through-bolts.
 - Possible to use SS end-flange for compression to further reduce
   chamber through holes?
 - Chuck and Tim need O.D. and I.D. of the frame annulus.  Need to
   work with the board designer to finalize annulus size.

2). Cathode Board Update:

   Flex board manufacturer can make boards up to 60in wide.  Brian
   is working to identify a kapton vendor.  He will have word by
   Friday.
 - Brian expects that our flex boards for the mechanical mock-ups
   can be done by the end of the year.
 - DSC suggested to proceed with sandwich construction using kapton
   blanks.  We will want to see how quickly the sandwich can be
   put together.
 - Dummy flex board design was completed by Jeff Wilson last week.
   Boards can be sent out as soon as kapton source is identified.

3). Full-Scale Tensioning System:

   Brian is nearly ready to contact the shop to have full-scale
   tensioning system constructed.

4). g10 Source:

   Brian has identified g10 source and the frame construction can
   proceed once the design is completed.

5). Daughter Boards:

   Simon is looking into connectors for the daughter board.  5-mm
   spacing may be an issue.  DSC instructed that he talk to Chris
   Cuevas.

6). Budget Work:

   Simon is working on improving our budget estimates for FDC
   construction.  We will go over his work tomorrow.

Minutes prepared by Daniel. Send any comments or corrections along.