Agenda

  1. Production Construction Tracking (Dave)
  2. Cathode corrosion
    • Recent test results: [1]
    • Cathode foil coating
  3. Engineering (Bill)
  4. Electronics (Chris, Nick)
  5. Third package tests FDC E-log (Beni)
  6. TDR, pages 132-145 (Lubomir)
  7. Other


Minutes

Participants: Eugene, Bill, Dave, Simon, Vlad, Beni, and Lubomir

Production

- Dave: Need to put the cards on another two cathodes and we will be ready with the first three cells that will go in package #1. Chris put the resistors on one PCB set and Casey started today making the PCB ring for wire frame #28. It will be laminated beginning of next week and Anatoly will put and test the HV caps before the end of the next week.

- Eugene: in order to expedite the solenoid testing, the plan so far is that three of our techs will be taken from us for two months, October and November. Dave and Anatoly will still work on the FDC. In case we need somebody for a short time, like half a shift, we should discuss this with Tim and Tom in advance.