Line 27: Line 27:
 
- Dave: Tina is soldering wire frame #29. Mike is working on the PCB ring for #30. Five new g10 wire frames (we asked for four) were made by Vision machine, then we laminated the Rohacel rings and sent them back to Vision for the fly cut.
 
- Dave: Tina is soldering wire frame #29. Mike is working on the PCB ring for #30. Five new g10 wire frames (we asked for four) were made by Vision machine, then we laminated the Rohacel rings and sent them back to Vision for the fly cut.
  
- Vlad: testing the first three cells of package #1. The oxygen went down to 170ppm, we started flushing on Sunday. All the channels were tested with a source and scope and are working fine. One pre-amp card was noisy, has to be replaced.   
+
- Vlad: testing the first three cells of package #1. The oxygen went down to 170ppm, we started flushing on Sunday. All the channels were tested with a source and scope and are working fine. One pre-amp card was noisy, has to be replaced. Currents are higher in all the cells:    
  
- The first three cells of package #1 were assembled Monday-Tuesday using the standard Viton+Apiezon technique. Since then it's being flushed with gas. Oxygen goes down very fast, now it's about 1000ppm and expect it to be ~300ppm tomorrow so Vlad will start testing the package.
+
- Lubomir: on Sunday Vlad found the gas bottle at Blue Crab supplying gas to the first package and the testing vacuum chamber, was empty due to high consumption of the testing chamber. The vacuum pump
  
 
== Cathode corrosion ==
 
== Cathode corrosion ==

Revision as of 17:18, 27 September 2012

September 27, 2012 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • First package tests (Vlad)
  2. Cathode corrosion
  3. Engineering (Bill)
  4. Electronics (Chris, Nick)
  5. Third package tests FDC E-log (Beni)
  6. TDR, pages 132-143 (Lubomir)
  7. Other: plots for Eugene's talk