Difference between revisions of "Minutes-9-19-2013"

From GlueXWiki
Jump to: navigation, search
Line 22: Line 22:
 
- The techs will start soon the installation of the FDC platform. The space between the two rails on the platform (holding the carts) is very small, it will be very difficult to work at the bottom side of the packages. The racks have not been installed yet, first cable holes have to be cut. The electronics will not be installed until all the dirty work is finished.
 
- The techs will start soon the installation of the FDC platform. The space between the two rails on the platform (holding the carts) is very small, it will be very difficult to work at the bottom side of the packages. The racks have not been installed yet, first cable holes have to be cut. The electronics will not be installed until all the dirty work is finished.
  
- We discussed a lot if the BCAL cabling and infrastructure  installation will interfere with the FDC installation. Bill: before we can start cabling FDCthe water ring (for the cooling) has to be installed on the bore of the magnet. It's not clear if the Nitrogen cooling, cables for the control system, also has to be installed in advance. Not all of these subsystems are ready, some has not been decided yet. Beni proposed to ask Elton to explain their plans on the next FDC meeting so that we can synchronize our activities.   
+
- We discussed a lot if the BCAL cabling and infrastructure  installation will interfere with the FDC installation. Bill: certainly prior to the FDC installation the two cooling rings (manifolds) have to be installed; the whole cooling system have to be tested. The signal cables It's not clear if the Nitrogen cooling, cables for the control and monitoring system also have to be installed in advance. Not all of these subsystems are ready, some have not been decided yet. Beni proposed to ask Elton to explain their plans on the next FDC meeting so that we can synchronize our activities. Certainly prior to the FDC installation the two cooling rings (manifolds) have to be installed  
  
  

Revision as of 17:12, 19 September 2013

September 19, 2013 FDC meeting

Agenda

  1. Installation preparations [1] (all)
  2. Engineering (Bill)
  3. Electronics (Chris, Nick)
  4. Tests in EEL126
    • New F1TDC (Beni)
    • Thick cell analysis (Vlad) [2],[3]
  5. Other