June 2, 2011 FDC meeting

Agenda

  1. Production (Dave)
    • First chamber assembly: HV problem
    • Spacer ring: gas leakage
    • Second set wire frame and cathodes
    • Other
  2. Engineering (Bill)
    • Vacuum chamber
    • Ultrasonic cleaning
    • Rigid-flex gluing tool
    • Other
  3. Electronics (Fernando, Chris)
    • PCB schematics update
    • Other
  4. Chamber testing
    • Wire Position Measurements
  5. Other

Minutes

Participants: Eugene, Bill, Dave, Chris, Caleb, Beni, Simon, and Lubomir.

Production

- End of last week we assembled the first production chamber, run gas over the weekend, on Monday applied HV and was tripping (1uA threshold) at very low voltages: ~20-30V for sense wires and somewhat higher (~30V, one sector was at -500V for short time) for field wires. Then we found ~1-10MOhm between HV and ground and practically all the pads on the PCBs, even between opposite PCBs on the wire frame that have no electrical connection. The conclusion was: the wire frame got wet (most likely the Rohacell) when it was cleaned in the ultrasonic bath. We tried to dry it with a lamp and then with a heat gun; didn't work. Then today we put it a big vacuum chamber at the Test Lab to take the moisture out. The person servicing the vacuum chamber mentioned that it went down to 10^-4 torrs for ~2hours, much slower than usual (~20min) which indicates there was a lot of moisture there.