Difference between revisions of "Minutes-6-23-2011"

From GlueXWiki
Jump to: navigation, search
Line 25: Line 25:
 
== Production ==
 
== Production ==
  
- Dave (see the Construction Tracking link above): first
+
- Dave (see the Construction Tracking link above): cell#2 is ready, including one end window. Anatoly cleaned the wire frame manually. Second end window will be ready tomorrow. Will start very soon stacking the package, but need some parts. Cell#3: position measurements on the wire frame (Caleb and Al made a code that does it automatically, but has not been tested yet), making flaps on one of the cathodes and gluing rigid-flexes on the other one. Cell#4: wire frame is ready for stringing, one of the cathoed is being tensioned and the foil for the second is in preparation.  
- The pictures linked above, show the configuration of the first chamber package and the testing set-up. After taking the wire frame form the vacuum chamber (vacuum went down to ~6 10^-6 tor) we checked that the frame was no longer conductive and we installed it again in the package. First we had Lexan sheet on the top, than we replaced it with the second cathode and the second end window. The package has no detectable gas leakage and we bubble it with a flow of 20-40 ccpm. On three of the HV sectors (out of four) we were able to apply HV up to 2300V and -500V sense/field with current less than 100 uA. The fourth HV sector shows high current so far: ~500 uA at 2000V/-500V. It may improve, but if not, it will require cleaning. In any case the chamber is operational and we tested all the channels with a scope with differential probe. In the moment we see signals from all the channels (both wires and strips) except one cathode channel on the bottom cathode which connectors are close to a metal pin. We suspect it was damaged when prying the wire frame with a screw driver when it was taken to be put in the vacuum chamber. The pins are very tight (compared to the prototype) and the only way to take a frame out was to rotate the pins while lifting the frame; for that you need to unscrew the hubs from the jig plate. Bill will work on designing pins that are easily removable. Before, there were also another two channels on the top cathode not showing signals but after bending a little the cathode periphery at the daughter card it started working (has to be investigated!).  At the beginning of the tests most of the noise was coming from the chamber itself, but later it improved. Generally, the pick-up noise is much lower than on the full-scale prototype. Could be because of the new design cathode shielding, and/or because Blue Crab is less noisy than 126.
+
  
- Dave summarized the production progress on the spreadsheet linked above. Techs are working on the second and third cells that will be part of the first package. Remaining for cell#2: tomorrow Chris will put the second phase elements on the wire frame and then we will clean it manually with alcohol. Casey will glue the rigid-flexes. Anatoly is working on the flaps of one of the cathodes and the end windows. Mike and Tina are working on the gas spacer and next cathode foils. On Tuesday we can start assembling the package. Techs were working also on different tooling: Casey made lazy-Susan for attaching the cathodes and gluing rigid-flexes. Al and Caleb are testing/writing software for the new encoder.
+
- We discussed if we can relax the clean room humidity requirements to save on the energy bill. The main concern are the gluing operation and the Rohacell material being
  
 
== Engineering ==
 
== Engineering ==

Revision as of 17:19, 23 June 2011

June 23, 2011 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • Second and third cell status
    • Humidity requirements (related to possible changes of the AC settings)
    • Other: using radioactive source at Blue Crab
  2. Engineering (Bill)
    • Wire deadening Sasha's doc (page 13, Fig.14)
    • Package cabling
    • Other
  3. Electronics update (Fernando, Chris)
  4. Chamber testing at EEL126 (Beni, Lubomir)
    • First cell status
    • DAQ and software
  5. Other