= Minutes =
 
= Minutes =
Line 27: Line 25:
 
== Engineering update ==  
 
== Engineering update ==  
  
- Caleb: Bill is busy, but he explained well details of the outer (outside of the FDC) part of the cooling system that will have Fluorinert and water loops. Caleb will work with Bill also on the testing of the cooling system.  
+
- Without Bill we discussed the grounding hardware: if we want to use Rohacell or the rubber material suggested by Bill for filling the void between wire and cathode frames. Since we will have of the order of 100 such blocks per package, Simon said it's too much material and we better use Rohacell.  
  
 
== Electronics update ==
 
== Electronics update ==
  
- Chris: LV cables have come. We discussed that it is worth setting up the LV system in 126 and later connecting the LV cables to the third package (when it will be in 126) but not applying voltage on most of them since we will need cooling.  
+
- Nick: no news, waiting for different parts, grounding clips, LV stuff, to come.  
  
== Cable assignment and labeling ==
+
== Cable assignment ==
  
- See the document above prepared by Vlad. It contains (in Excel format) a table of all the signal cables showing the label and the destination rack, crate, module, and connector. There's a scheme at the end of the document: half of the cables will go to the left and half to the right racks depending where the corresponding card is. Wire cables will be connected to F1TDCs, 6 modules per package per side occupying two crates with 12 modules each. 5 crates on each side will be filled with 15/14 fADC125s, having 18 modules per package per side. We decided to keep the channel information in the label (like FDC1,C5,D85B-108B).
+
- Vlad showed the new scheme linked above. First, wire/strip pre-amp cards are classified according to their rate levels. Wires: level 1 for the side connectors 1 and 4, and level 2 for the central connectors 2 and 3. Every F1TDC module (two connectors) has always one level 1 and one level 2 card. Strips: level 1 for connectors 1 and 8, level 2 for 2 and 7, level 3 for 3 and 6 and level 4/4' for 4,5/9 (the three central sectors). Each fADC125 (three connectors) is connected to either 4-1-3 card levels or 4'-2-2. In addition cards from different packages are combined already on module level to equalize the rate difference in the different packages, the latter estimated to be ~20%.  
  
- The ordering of the connectors is generally (from left to right in the crates) starting from the lower package, cell number, channel number. Beni suggested that we may want to split the cards with highest rates into different fADC modules. It's easy to implement, but we want to discuss this with Fernando, Cody, Gerard.
+
- The presented scheme obviously confused many on the meeting since already on module/crate level you have mixture of crates, cells, sectors. Eugene insisted that if the package variation is relatively small we better have some order with respect to package/cell number when assigning modules/crates for them. The advantage of such scheme is also that we have better chances to keep the cables bundled up to the electronics, since cables from the different packages will end at different distances. Vlad will modify the scheme by assigning the cables from a package to a group of modules close together.
 +
 
 +
- Related to the cabling we discussed how the installation will be done in such a way that the cables will stay connected to the electronics. Without Tom, Tim or Bill our discussion was not very efficient. It was not clear for us how much extra cable will be needed during the installation and where will it go after that, how the installation carts will be removed minimazing the probability to damage the cables and so on. We will invite Tom/Tim for the next meeting to discuss this. What was clear for us is that mixing cables from different packages will make the installation even more difficult.
  
 
== Gas system ==
 
== Gas system ==
  
- Beni is in contact with Narciso; soon we will have separate meeting about the gas system.   
+
- Beni: Narciso is working on the system; expect specialized meeting soon soon.   
  
 
== Test set-up at 126 ==
 
== Test set-up at 126 ==
  
- Beni: CODA-Light doesn't work with Linux ROCs so far. Will talk to Bryan Moffit if something can be done, if not possible we will have to move to the "heavy" CODA.
+
- Beni: Elliot is working on CODA-Light for the two-crate system.
 
+
- Vlad tested the cathodes of the top three cells of the first package in 126 with a source. The main complain is that on some of the channels there are no signals, but after unscrewing the card from the cooling tube it starts working. It is not clear why: probably the tube pulls/bends the card or the cathode frame. There were suggestions to tighten the tubes to the package evenly around the periphery with cables ties using the holes on the cathodes. Will be discussed with Bill.
+
   
+
== Other ==
+
 
+
- Lubomir looked at some old runs with the second production chamber where we have used also 55Fe source and triggered with one strip. We don't have long tails in the signals (including with comics) as seen in the CDC with fADC125.
+
  
-->
+
- Vlad tested so far the cathodes of 3.5 cells on the first package. One bad pin on a LV connector found.

Latest revision as of 10:52, 22 June 2012

June 21, 2012 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • Production status
    • Spare wire frames (Lubomir)
  2. Engineering update
  3. Electronics update (Chris)
  4. Cable assignment (Vlad)
  5. Gas system (Beni)
  6. Test set-up in 126 (Beni)
  7. Other

Minutes

Participants: Eugene, Dave, Nick, Vlad, Simon, Beni, and Lubomir.

Production

- Dave: Fourth cell was installed yesterday in the fourth package. Working also on several spare cathodes. Right after the meeting we installed the fifth one. The plan was to install the last cell on Friday, however, after the meeting we found a bad channel (cut on copper trace) on one cathode that will require more time for fixing; therefore we will finish with the fourth package installation on Monday.

- The second production wire frame: there was a bad HV sector showing ~20MOhm field to sense wires resistance while the other three were OK. Two wires, which pads were covered by the copper sulfide spill there, were replaced by Casey including the epoxy around them that was most likely contaminated by the chemical. After that we measured the resistance: about 20-30 MOhm and 50-100 MOhm on the other sectors. We recalled that on the first four wire frames we used Epolite that is susceptible to humidity. After flushing the wire frame with gas since Monday today we were able to put 2100/-500V with ~800/-500nA currents, still high but we hope the epoxy will dry and the currents will go down. So far we have one wire frame that can't be used. Eugene suggested not to postpone too much the ordering of the four extra PCB sets.

Engineering update

- Without Bill we discussed the grounding hardware: if we want to use Rohacell or the rubber material suggested by Bill for filling the void between wire and cathode frames. Since we will have of the order of 100 such blocks per package, Simon said it's too much material and we better use Rohacell.

Electronics update

- Nick: no news, waiting for different parts, grounding clips, LV stuff, to come.

Cable assignment

- Vlad showed the new scheme linked above. First, wire/strip pre-amp cards are classified according to their rate levels. Wires: level 1 for the side connectors 1 and 4, and level 2 for the central connectors 2 and 3. Every F1TDC module (two connectors) has always one level 1 and one level 2 card. Strips: level 1 for connectors 1 and 8, level 2 for 2 and 7, level 3 for 3 and 6 and level 4/4' for 4,5/9 (the three central sectors). Each fADC125 (three connectors) is connected to either 4-1-3 card levels or 4'-2-2. In addition cards from different packages are combined already on module level to equalize the rate difference in the different packages, the latter estimated to be ~20%.

- The presented scheme obviously confused many on the meeting since already on module/crate level you have mixture of crates, cells, sectors. Eugene insisted that if the package variation is relatively small we better have some order with respect to package/cell number when assigning modules/crates for them. The advantage of such scheme is also that we have better chances to keep the cables bundled up to the electronics, since cables from the different packages will end at different distances. Vlad will modify the scheme by assigning the cables from a package to a group of modules close together.

- Related to the cabling we discussed how the installation will be done in such a way that the cables will stay connected to the electronics. Without Tom, Tim or Bill our discussion was not very efficient. It was not clear for us how much extra cable will be needed during the installation and where will it go after that, how the installation carts will be removed minimazing the probability to damage the cables and so on. We will invite Tom/Tim for the next meeting to discuss this. What was clear for us is that mixing cables from different packages will make the installation even more difficult.

Gas system

- Beni: Narciso is working on the system; expect specialized meeting soon soon.

Test set-up at 126

- Beni: Elliot is working on CODA-Light for the two-crate system.

- Vlad tested so far the cathodes of 3.5 cells on the first package. One bad pin on a LV connector found.