− | - Bill | + | - Bill, Casey and Beni performed the test of one loop of the cooling system. 22 pre-amps were attached to the cooling tube and powered with LV. The flow (at the right pressure) appeared to be in a good agreement with the ANSI model, however the temperature drop between the end and the beginning of the loop was 1.2deg instead 2deg as expected from the model. We discussed possible reasons for that: |
− | + | ||
== Full electronics tests == | == Full electronics tests == | ||
Revision as of 17:15, 23 May 2013
May 23, 2013 FDC meeting
Agenda
- Production Construction Tracking
- Spare package status
- Update on the corrosion test at MePhi results (Lubomir)
- Engineering (Bill)
- Cooling system status and tests
- Electronics (Chris, Nick)
- Full electronics tests FDC E-log (Beni)
- Other