(Created page with "May 16, 2013 FDC meeting = Agenda = # Production [http://www.jlab.org/Hall-D/detector/fdc/production/FDC_Construction_May_16_2013.xlsx Construction Tracking] (Dave) #* Spare pac...")
 
m (Text replacement - "/halldweb1.jlab.org/" to "/halldweb.jlab.org/")
 
(7 intermediate revisions by 2 users not shown)
Line 2: Line 2:
  
 
= Agenda =
 
= Agenda =
# Production [http://www.jlab.org/Hall-D/detector/fdc/production/FDC_Construction_May_16_2013.xlsx Construction Tracking] (Dave)
+
# Production [http://www.jlab.org/Hall-D/detector/fdc/production/FDC_Construction_May_16_2013.xlsx Construction Tracking]
 
#* Spare package status
 
#* Spare package status
 
# Installation (Lubomir, Bill)
 
# Installation (Lubomir, Bill)
Line 9: Line 9:
 
#* Cooling system status
 
#* Cooling system status
 
# Electronics (Chris, Nick)
 
# Electronics (Chris, Nick)
# Full electronics tests [https://halldweb1.jlab.org/elog-halld/FDC FDC E-log] (Beni)
+
# Full electronics tests [https://halldweb.jlab.org/elog-halld/FDC FDC E-log] (Beni)
 
# Other
 
# Other
 
<!--
 
  
 
= Minutes =
 
= Minutes =
  
Participants: Bill, Chris, Nick, Simon, Beni, and Lubomir.
+
Participants: Casey, Bill, Dave, Chris, Simon, Beni, and Lubomir.
  
 
== Production ==
 
== Production ==
  
- All the wire frames are deadened now.
+
- Spare package: interestingly the second cell with wire frame #6 showed the same problems as with wire frame #3 before: no signals on chan.1, point source of noise in one of the middle wires and glow discharge (sudden increase of the current on both sense and field wires). The difference is that the source of the noise was at the end of the wire (as picked up by the strips), and also that the glow discharge disappears when removing some of the cathode cards. All this was pointing that the problems are caused by the tip of the wire sticking out of the solder.
 +
As for chan.1 we looked at the previous wire frame #3 and found the HV resistor for wire #1 had a crack. On Tuesday we opened the top cell (with the help of Mark Bear) and found exactly what we expected. The cracked resistor was replaced, the solder pad re-flowed to cover the wire, and then we closed the package. Will start testing it on Friday afternoon; Dave will bring the NIM power supply that we share with the magnet people. The two wire frames #3 and #6 were done at the same time by the same people using same tools, obviously this explains the similarities in their problems.  
  
- Spare package installation: Two cells were installed last week. The bottom cell (wire frames #2) was tested and works fine, but the top one (wire frame #3) showed different problems: no signal on the first wire (suspect wire is broken between the pad and epoxy), point noise source on one wire, glowing discharge appearing from time to time at >2kV. The discharge can be identified by a sudden increase of the currents on both sense and field wires up to 1-10 uA that doesn't go away unless the voltage is decreased. Instead of trying to fix wire frame #3 we decided to replace it with wire frame #6. While testing #6 before the installation, two broken wires were found and then fixed by Casey in two days: one of the wires was giving somehow signals on the first day. Finally this morning we installed the second cell with wire frame #6 that will be tested on Monday.
+
- At the beginning of next week (most likely Tuesday) we will install two new cells (wire frames #27 and #28). The last two cells will have thicker spacers. We discussed what kind of holes we want to drill on these spacer rings to have the same pressure in the cells. The best is to have separate flow controller for the last two cells and to regulate the flow so that there's no big pressure difference between the cells. Bill propose to use a simple plastic part used in fans to spread the air. It will be mounted inside the spacer rings.
 
+
== Update on the corrosion test at MePhi ==
+
 
+
- Vlad sent us update about his latest results: the test at 65degC had six, only EPDM, samples (no chance to see some effects with Viton at this temperature) and they failed in between 30 to 54 hours.
+
In the first test (at 100degC) the two EPDM samples were found with high resistivity in 8 and 24 hours, but the latter sample wasn't tested in between. Therefore Vlad decided to repeat the test at 100degC only with EPDM samples (six) but this time checking the samples more often in the first 24 hours.
+
  
 
== Installation ==
 
== Installation ==
  
- The draft of the installation document is ready and linked above. Beni wrote the section about the DAQ and trigger requirements for the FDC test outside of the magnet. One can use the document when writing the installation procedures; there are enough details for that. Bill (probably also with Tim) will look at the paper and will give us his/their recommendations/changes/remarks.  
+
- Mock-up: Casey adjusted and connected all the eight rails of the two carts at Blue Crab, now we can continue with the test putting the packages on the cart. Before that (next Wednesday) Casey with the help of Bill will make one of the inter-package spacers to install it between two of the packages.
 
+
- In particular we discussed that frames that will support the top and bottom scintillator planes (each with two paddles) needed for the testing. Beni will give Bill information about the paddles and Bill will sketch the frames.
+
  
 
== Engineering ==
 
== Engineering ==
  
- Casey replaced the manifolds on package #3 with aluminum ones and then the cooling system was tested with 100 psi pressure from the CO2 bottle: no leakage found with the sniffer.
+
- Bill: there are problems with the water chiller; Mike Sprouse suggested several things: to measure the temperature at the input and output of the chiller and estimate the heat produced by the chiller itself. He suggested also to clean the heat exchanger. Another option is to find another water chiller. After the meeting Bill with Casey found that the water chiller itself is producing a lot of heat, therefore Bill borrowed another chiller from the accelerator people. So, the plan now is to replace the water chiller which will happen at the beginning of next week.
 
+
- Bill about the cooling system test at 126: yesterday we tested the system with Fluorinert, now with aluminum manifolds no leakages were found except at some points on the copper tubing where it was machined (drilled to increase the inner diameter). However, the water chiller appeared to have a problem when working with the SMC chiller. The SMC chiller stops the flow of the cold water from time to time when it's not needed. In case of no water flow, the pump of the water chiller starts heating and the water temperature increases up to 45degC. To fix the problem Bill wants to bypass the SMC chiller if it blocks the water and is working on that. Another option will be to replace the pump with another type, but will cost more. 
+
     
+
== Full electronics tests  ==
+
 
+
- Beni: Cody and Bryan still working on the firmware/software for fADC125. Beni will get more cables from Nick for the LV system in 126.
+
  
- After the meeting Eugene proposed to install the third package in 126, install all the fADC125s needed, and connect them with cables. Even if we can't read now the new fADCs we can look at the noise of the old fADC125s that we can read. The problem is that the modules may have to be moved back to Cody to install the firmware. Beni will talk to Cody and Brian about this option, but in any case we plan the move the third package next week.
+
== Full electronics tests ==
  
-->
+
- Beni: no news for the firmware of fADC125. The plan is to move the third package on Monday. If the firmware/software is not ready by the end of next week we will get the modules from Cody as they are and read out only the old modules.

Latest revision as of 01:06, 1 April 2015

May 16, 2013 FDC meeting

Agenda

  1. Production Construction Tracking
    • Spare package status
  2. Installation (Lubomir, Bill)
    • Update on the mock-up
  3. Engineering (Bill)
    • Cooling system status
  4. Electronics (Chris, Nick)
  5. Full electronics tests FDC E-log (Beni)
  6. Other

Minutes

Participants: Casey, Bill, Dave, Chris, Simon, Beni, and Lubomir.

Production

- Spare package: interestingly the second cell with wire frame #6 showed the same problems as with wire frame #3 before: no signals on chan.1, point source of noise in one of the middle wires and glow discharge (sudden increase of the current on both sense and field wires). The difference is that the source of the noise was at the end of the wire (as picked up by the strips), and also that the glow discharge disappears when removing some of the cathode cards. All this was pointing that the problems are caused by the tip of the wire sticking out of the solder. As for chan.1 we looked at the previous wire frame #3 and found the HV resistor for wire #1 had a crack. On Tuesday we opened the top cell (with the help of Mark Bear) and found exactly what we expected. The cracked resistor was replaced, the solder pad re-flowed to cover the wire, and then we closed the package. Will start testing it on Friday afternoon; Dave will bring the NIM power supply that we share with the magnet people. The two wire frames #3 and #6 were done at the same time by the same people using same tools, obviously this explains the similarities in their problems.

- At the beginning of next week (most likely Tuesday) we will install two new cells (wire frames #27 and #28). The last two cells will have thicker spacers. We discussed what kind of holes we want to drill on these spacer rings to have the same pressure in the cells. The best is to have separate flow controller for the last two cells and to regulate the flow so that there's no big pressure difference between the cells. Bill propose to use a simple plastic part used in fans to spread the air. It will be mounted inside the spacer rings.

Installation

- Mock-up: Casey adjusted and connected all the eight rails of the two carts at Blue Crab, now we can continue with the test putting the packages on the cart. Before that (next Wednesday) Casey with the help of Bill will make one of the inter-package spacers to install it between two of the packages.

Engineering

- Bill: there are problems with the water chiller; Mike Sprouse suggested several things: to measure the temperature at the input and output of the chiller and estimate the heat produced by the chiller itself. He suggested also to clean the heat exchanger. Another option is to find another water chiller. After the meeting Bill with Casey found that the water chiller itself is producing a lot of heat, therefore Bill borrowed another chiller from the accelerator people. So, the plan now is to replace the water chiller which will happen at the beginning of next week.

Full electronics tests

- Beni: no news for the firmware of fADC125. The plan is to move the third package on Monday. If the firmware/software is not ready by the end of next week we will get the modules from Cody as they are and read out only the old modules.