== Engineering ==
 
== Engineering ==
  
- Bill is finalizing the fiducial scheme  
+
- Bill is finalizing the fiducial scheme: will have 4 fiducial holders on each package visible at all times. Difficulties finding non-magnetic low-mass materials. Eugene and Beni had different suggestions especially concerning the z-position determination. Bill will coordinate his plan with the survey group. Bill is working also on the spacer between the packages, decided to have 3 supporting rods instead of 4, 
  
 
== Electronics ==
 
== Electronics ==
  
- Beni asked when the checking of all the pre-amps will be finished; he is interested actually in the fADC125 that is used in the tests. Beni's idea is to use at least the two available fADC125 to test the cathode channels on the first package; non of them is connected now.
+
- Chris: there's a plan
 
+
- Chris: in principle this can be done within few weeks. We will discuss this with Fernando.
+
  
 
--->
 
--->

Revision as of 15:41, 6 April 2012

April 5, 2012 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • New procedures for the O-ring replacements
    • Production status
  2. Results from the oxygen studies (Lubomir)
  3. Engineering update (Bill)
  4. Electronics update (Chris)
  5. Possibilities for cluster counting (Lubomir)
  6. Other