== Installation ==
 
== Installation ==
  
- Starting from this meeting we will have discussions about the FDC installations. The installation schedule linked above was made with FastTrack using the rebaseline-d schedule. Items not for FDC, but related/needed for the FDC installation (predecessors) are also included.  
+
- Starting with this meeting we will have discussions about the FDC installations. The installation schedule linked above was made with FastTrack using the rebaseline-d schedule. Items not for FDC, but related/needed for the FDC installation (predecessors) are also included.  
  
 
- First, it's not clear when we have to move out from Blue Crab. It was decided end of last year that the lease will be extended by one month (till Sep.23), but whether this will be done and how much time facilities need to remove everything from there is not clear. For now we plan to stay there (at least to keep the FDC packages) till Aug. 23. If this is not the case we have find a good temporary place for the FDC. We were talking also about what will haven with the clean room; everybody says destroying it will be wasting of a lot of money. We also have to find space for all the equipment/tooling so that we will be able to do fixes later if needed. Chris proposed to bring the most valuable tooling to 117.
 
- First, it's not clear when we have to move out from Blue Crab. It was decided end of last year that the lease will be extended by one month (till Sep.23), but whether this will be done and how much time facilities need to remove everything from there is not clear. For now we plan to stay there (at least to keep the FDC packages) till Aug. 23. If this is not the case we have find a good temporary place for the FDC. We were talking also about what will haven with the clean room; everybody says destroying it will be wasting of a lot of money. We also have to find space for all the equipment/tooling so that we will be able to do fixes later if needed. Chris proposed to bring the most valuable tooling to 117.

Revision as of 17:03, 7 March 2013

March 7, 2013 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • Spare parts
    • Package #2 status
    • Package #3 repair
  2. Rebaselining update [1](Lubomir)
  3. Installation schedule (Lubomir)
  4. Engineering (Bill)
    • Manifold installation
  5. Electronics (Chris, Nick)
  6. Tests at EEL126 FDC E-log (Beni)
  7. Other

Minutes

Participants: Bill, Dave, Chris, Nick, Simon, Beni, and Lubomir.

Production

- Dave: one more cathode with the daughter cards installed. Chris and Nick finished the HV cabling/connectors for the last package (#2). The package is ready for testing, just have to install it on the strong-back and also drill holes in the end-window to attach the HV cables at the bottom. The PR for Vision Machine (for the gas blocks and thick spacers) went through, Adam already contacted Bill with this respect.

- We are planning to fix the HV problem in package #3 starting next week when the mounting table will be available. The problematic HV sector (#2, 20 wires) is in plane 6 (not 5! as in the previous minutes), so it will be easier since we will open it from the back of the package. Bill agrees this is doable.

Rebaselining update

- For all of the FDC activities there are links in the above html file, explaining the scope, resources and bases for estimates. Within these links for some of the items there are additional links to documents used for these estimations. There are some items we were not sure about like: 25211210 (materials for cooling), 25211215 (materials for alignment/fiducials), 25211216 (materials for HV connectors). Bill thinks all the materials for the first two have been ordered. As for the HV connectors, we have all the connectors that we need for the FDC (Nick).

Installation

- Starting with this meeting we will have discussions about the FDC installations. The installation schedule linked above was made with FastTrack using the rebaseline-d schedule. Items not for FDC, but related/needed for the FDC installation (predecessors) are also included.

- First, it's not clear when we have to move out from Blue Crab. It was decided end of last year that the lease will be extended by one month (till Sep.23), but whether this will be done and how much time facilities need to remove everything from there is not clear. For now we plan to stay there (at least to keep the FDC packages) till Aug. 23. If this is not the case we have find a good temporary place for the FDC. We were talking also about what will haven with the clean room; everybody says destroying it will be wasting of a lot of money. We also have to find space for all the equipment/tooling so that we will be able to do fixes later if needed. Chris proposed to bring the most valuable tooling to 117.

- The rails on the platform have to be installed before the FDC appears in the Hall.