Difference between revisions of "Minutes-2-27-2014"

From GlueXWiki
Jump to: navigation, search
Line 24: Line 24:
 
== Engineering ==   
 
== Engineering ==   
  
- Bill returned from Hexagon Metrology, Charlotte, NC, and showed us
+
- Bill returned from Hexagon Metrology, Charlotte, NC, and showed us pictures of the MCC machine and a lot of data: the xlsx file is attached above containing all the raw data. The cathodes were scanned automatically along the strips recording the edges of the strips
  
 
- Dave started working on the hardware shut off of the LV crate from the chiller. He needs to identify how exactly to interpret the signals about the chiller status and then will figure out with Fernando what the PCB should be doing. The board can be mounted on the same rack (back side) where the LV crate is. As for the MPOD controller settings Dave will talk to Hovanes.
 
- Dave started working on the hardware shut off of the LV crate from the chiller. He needs to identify how exactly to interpret the signals about the chiller status and then will figure out with Fernando what the PCB should be doing. The board can be mounted on the same rack (back side) where the LV crate is. As for the MPOD controller settings Dave will talk to Hovanes.

Revision as of 18:51, 27 February 2014

February 27, 2014 FDC meeting

Agenda

  1. Installation status [1]
  2. Engineering (Bill, Dave)
    1. Cathode scan
    2. LV fast shutdown
  3. Electronics problematic channels (Fernando, Chris, Nick)
  4. Mini-DAQ status FDC E-log (Beni)
  5. Other