Difference between revisions of "Minutes-12-2-2010"

From GlueXWiki
Jump to: navigation, search
Line 38: Line 38:
  
 
- Roger who is now at the Allflex facility in Minnesota, informed us that the production of the first foils started. On Tuesday two panels were produced, one of them developed a wrinkle during the photo-resist stripping. We can still use such foils for practicing; it's good we have a lot of spare material. We don't know yet when they are going to ship the first article. Still, we decided to move two tables inside the Hall B clean room tomorrow afternoon, so that we have the place ready for the foil inspection.
 
- Roger who is now at the Allflex facility in Minnesota, informed us that the production of the first foils started. On Tuesday two panels were produced, one of them developed a wrinkle during the photo-resist stripping. We can still use such foils for practicing; it's good we have a lot of spare material. We don't know yet when they are going to ship the first article. Still, we decided to move two tables inside the Hall B clean room tomorrow afternoon, so that we have the place ready for the foil inspection.
 +
 +
 +
- Bill informed us about accelerated aging tests done with the 3M conductive tape: the specialists are confident that it will last for 10 years, but the company is not going to state this officially. Bill will try another type (7303) of such tape that has pure epoxy.
  
 
== Engineering ==
 
== Engineering ==
Line 47: Line 50:
 
- The controller for the stepper motor should be here within a week. Two people representing Acuity were at JLab today demonstrating their laser sensors. It turned out that the new sensor that has higher sampling rate (9.6kHz compared to 1.2kHz that we have now) has bigger spot size and doesn't see the 25um wires on the first prototype. They proposed to use another two-dimensional sensor but it is not clear if it can see our wires, and also the price is high. Casey will string several field wires with the nominal tension of 20g directly on the granite table, and we will try to measure the tension using our laser sensor.   
 
- The controller for the stepper motor should be here within a week. Two people representing Acuity were at JLab today demonstrating their laser sensors. It turned out that the new sensor that has higher sampling rate (9.6kHz compared to 1.2kHz that we have now) has bigger spot size and doesn't see the 25um wires on the first prototype. They proposed to use another two-dimensional sensor but it is not clear if it can see our wires, and also the price is high. Casey will string several field wires with the nominal tension of 20g directly on the granite table, and we will try to measure the tension using our laser sensor.   
  
-
 
  
 
== Full-scale prototype tests ==
 
== Full-scale prototype tests ==

Revision as of 18:01, 2 December 2010

December 2, 2010 FDC meeting

Tentative Agenda

  1. Production (David)
  2. Electronics (Fernando, Chris)
    • PCB status
    • Cathode foil production
    • Other
  3. Engineering (Bill, David)
  4. Full-scale prototype
  5. Other


Minutes

Participants: Bill, Chris, Glenn, Eugene, Dave, Simon, Beni, and Lubomir.

Production

- Blue Crab status: the clean room construction started this week, walls are erected already.

- Wire frames (Bill): all wire frames inspected, we have 30 ready to go (out of 32), one is a little off the specifications, and another one is way off. Next step: gluing and laminating the PCBs that should start next week at Blue Crab. 16 cathode frames are ready; important is to check the depth of the O-ring groove.

- New schedule: we discussed the feasibility of the package full tests scheduled to start at the beginning of 2012. For that we will need enough electronics to equip one full package: 12 F1TDCs, 36 fADCs, 24 anode and 108 cathode cards. According to Fernando we will have the cards and the fADCs by June 2012 and the F1TDCs by Sep 2012. Eugene looked at the last schedule for the electronics and concluded that actually we will have a good fraction of the electronics ready by the beginning of 2012. A delay is expected with the F1TDCs and we discussed options to replace those with other types of TDCs. Beni raised the question about the additional modules needed for the DAQ, since we are going to have at least two crates. All these questions require additional information from Fernando and other people, so we will continue the discussion off-line and on the next meeting.

Electronics

- Chris cleaned and tested with 2500V channel by channel all the first article PCBs. So, now we have two sets of PCBs ready to be laminated. For the cleaning, he used first Vigon bath but was not enough, so he did the final cleaning with Flux-off bottles. The rest of the PCBs that were sent back to the company for cleaning are still there. Fernando ordered two solder types for the wire soldering that we will test.

- Roger who is now at the Allflex facility in Minnesota, informed us that the production of the first foils started. On Tuesday two panels were produced, one of them developed a wrinkle during the photo-resist stripping. We can still use such foils for practicing; it's good we have a lot of spare material. We don't know yet when they are going to ship the first article. Still, we decided to move two tables inside the Hall B clean room tomorrow afternoon, so that we have the place ready for the foil inspection.


- Bill informed us about accelerated aging tests done with the 3M conductive tape: the specialists are confident that it will last for 10 years, but the company is not going to state this officially. Bill will try another type (7303) of such tape that has pure epoxy.

Engineering