Line 18: Line 18:
 
== Installation preparations ==
 
== Installation preparations ==
  
- Pictures linked above show the current status of the FDC platform in the Hall. The first cart has been installed on the platform and the survey people aligned the rails inside BCAL with the rails on this cart.  
+
- Pictures linked above show the current status of the FDC platform in the Hall. The first cart has been installed on the platform and the survey people aligned the rails inside BCAL with the rails on this cart. The cooling manifold for the BCAL on the upstream side of the magnet has not been installed yet but should be done soon (Bill). The racks on the left side (looking downstream) have been put in place, probably not finally installed. The holes below the racks on the right side have been marked but not cut. The mesh has not been modified yet. Holes in the beam below the platform have been made on the left side (right will be done soon, as well) and we discussed if the size is big enough for one bundle of 8/9 cables; the problem is that the connectors at this side are big and you have to un-bundle the end to insert the cables one by one. We will have ~18 bundles at one side, not sure if we have 18 holes.
 +
Also, we will need more people when pulling/pushing the cables through these holes.
 +
 
 +
- We discussed what to do with the systems that are absolutely needed for the FDC installation but will not be ready before the installation starts: gas, electric power and cooling. Gas: Dave will check what has been installed and how it can be modified. Beni: if some of the 500 ccpm flow controllers have been installed already then we don't have enough for a temporary gas system, i.e. we have to disconnect them 
 
   
 
   
 
== Engineering ==
 
== Engineering ==

Revision as of 17:37, 10 October 2013

October 10, 2013 FDC meeting

Agenda

  1. Installation preparations [1] (all)
  2. Engineering (Bill)
  3. Electronics (Chris, Nick)
  4. Tests in EEL126
  5. Other