Minutes-1-20-2011

From GlueXWiki
Revision as of 17:35, 20 January 2011 by Pentchev (Talk | contribs)

Jump to: navigation, search

January 20, 2011 FDC meeting

Tentative Agenda

  1. Production (David)
  2. Electronics (Fernando, Chris, Roger)
    • Rigid-flex assemblies
    • Foil production status
    • Other
  3. Engineering (Bill, David, Lubomir)
  4. Full-scale prototype studies
  5. Other

Minutes

Participants: Dave, Chris, Simon, Beni, Fernando, Glenn, and Lubomir.

Production

- Dave: there was a walk trough the clean room yesterday with the vendor. The emergency exit door must be sealed better. Glass on the dark room door must be covered. The move in date is postponed to Jan 31. Dave has prepared conduct of operation documents for the clean room.

- New ETC schedule: the full package testing is postponed and squeezed. Fernando: even with the new schedule we may not have the electronics needed for the tests, so we need to have alternative testing procedure.

Electronics

- Chris sent the first article signal cables back to the company to fix the cable problem.

- We discussed two issues with the rigid-flex assemblies: