Line 5: | Line 5: | ||
# Production (David) | # Production (David) | ||
#* Blue Crab status | #* Blue Crab status | ||
− | #* ETC [After_Snapshot_CR11-006_Hall_D_ETC_14_January_11_PMK_v2.pdf schedule] | + | #* ETC [http://www.jlab.org/Hall-D/detector/fdc/budget/After_Snapshot_CR11-006_Hall_D_ETC_14_January_11_PMK_v2.pdf schedule] |
# Electronics (Fernando, Chris, Roger) | # Electronics (Fernando, Chris, Roger) | ||
#* Rigid-flex assemblies | #* Rigid-flex assemblies |
Revision as of 12:20, 20 January 2011
January 20, 2011 FDC meeting
Tentative Agenda
- Production (David)
- Blue Crab status
- ETC schedule
- Electronics (Fernando, Chris, Roger)
- Rigid-flex assemblies
- Foil production status
- Other
- Engineering (Bill, David, Lubomir)
- Wire stringing FDC Log Book, page 549
- Movement control
- Other
- Full-scale prototype studies
- Latest tests (Lubomir)
- Other