Current planning is for a 1 1/2 day meeting the week of 7-May, with no parallel sessions.  This will be a combined Hall D and Hall B review.
 
Current planning is for a 1 1/2 day meeting the week of 7-May, with no parallel sessions.  This will be a combined Hall D and Hall B review.
  
 +
[[http://www.jlab.org/Hall-D/reviews/System_Review_May08/ | Review Website]]
  
 
==Charge for the Review Committee==
 
==Charge for the Review Committee==
  
No charge for the committee has been established yet (Apr 2008). A very broad possible charge, based on charges from previous reviews, might be:
+
Draft charge for the committee (see [http://www.jlab.org/Hall-D/guest_secure/System_Review_May08 here] for the latest):
  
  
The scope of this review includes all aspects of the following Hall D systems and components:  electronics, trigger, DAQ, event and hardware monitoring, experiment and detector controls, as well as detector infrastructure, integration, installation, maintenance, and safety considerations.  Performance requirements, development and construction schedules, costs, and ES&H issues may be reviewed for all systems, as well as any other considerations that may influence the construction and operation of the Hall D detector.
+
The scope of this review includes the Hall D electronics and data acquisition systems, the mechanical assembly and installation of the various Hall D detector elements, and the general infrastructure for this new experimental Hall.
  
In addition, for electronics systems the scope includes functional design, technology choice, fabrication considerations, testing and quality control, maintainability, and long-term viability.  For computing systems the scope includes computing architecture, network design, data flow issues, protocol choices, and network and computing hardware choices.  For software the scope includes functional design, complexity, coding and language concerns, testing and quality control, commissioning, operational concerns, and long-term maintainability.  For hardware the scope includes design philosophy, material selection, fabrication choices, levels of redundancy, commissioning procedures, costs for materials and labor, quality control, and operational reliability and longevity.
+
For the Hall D System and Infrastructure Design and Safety Review, you are asked to address the following questions:
  
You are asked to address the following questions:
+
# Are the technical performance requirements adequately defined for the systems under review? Are the plans for achieving technical performance and subsequent construction and testing sufficiently developed and documented for the present phase of the project?
 
+
#Are the plans to address recommendations of the recent Hall D detector system reviews sound and appropriately developed for this stage of the project?
1. Are the technical performance requirements adequate, appropriate, and complete for each system?
+
#Are the current designs and plans likely to achieve the performance requirements with a low risk of cost increases, schedule delays, and technical problems?
 
+
#Are the element fabrication and assembly plans consistent with the overall project and Hall D schedule?  Are the plans for the detector integration in the GlueX spectrometer and the associated Hall D infrastructure appropriately developed for the present phase of the project?
2. Do the current designs and plans appear likely to achieve the performance specifications with a low risk of cost increases, schedule delays, and performance problems?  Are there opportunities for improvements in cost or performance that the design teams should consider?
+
#Have ES&H considerations been adequately incorporated into the designs at their present stage?
 
+
3. Are the R&D efforts appropriate, complete, and likely to reduce risks?  
+
 
+
4. Have ES&H considerations been adequately incorporated into the designs and plans?
+
  
 +
Please address the above questions point-by-point.  Note that several aspects of the Hall D detector, electronics, and data acquisition systems have been reviewed previously. Recent 2008 reviews include a February Hall D Forward Drift Chamber mini-review, a February Hall D calorimetry review, and a March Hall D Drift Chambers and associated Particle Identification systems review. You will be supplied with the reports from these earlier reviews along with additional pre-briefing materials.
  
  
 
==Agenda==
 
==Agenda==
  
Possible agenda topics and speakers:
+
The current agenda can be found [http://www.jlab.org/Hall-D/guest_secure/System_Review_May08/Agenda.doc here.]
  
* Describe review process and committee charge - Allison or Rolf
 
* Intro to 12 GeV project - Allison or Rolf
 
* Intro to Hall D physics and detector - Elke or Elton
 
* Front-end electronics - Fernando and/or Chris
 
* Trigger - Dave D
 
* DAQ - Graham or Dave A
 
* Electronics/trigger/DAQ integration and monitoring/controls systems - Elliott
 
* Infrastructure, installation, assembly, maintenance, safety, etc. - Tim et al.
 
 
There may be additional short presentations on particular topics.
 
  
  
Line 50: Line 38:
 
* Prebrief outlines: 11-April  
 
* Prebrief outlines: 11-April  
  
 +
 +
==Remote Connection to the Dry Runs ==
 +
* When in F326/327, ESNET will be available.
 +
** ESNET: 8542553
 +
* Otherwise, phone connections will be provided.
 +
** Dial +1-800-377-8846 : US
 +
** Dial +1-888-276-7715 : Canada
 +
** Dial +1-302-709-8424 : International
 +
**Enter participant code: 39527048# (remember the "#")
 +
 +
==Dry Runs==
 +
 +
All Dry runs are in F326/327
 +
 +
* Wednesday 23rd of April:
 +
** 8:00am Graham [http://www.jlab.org/~heyes/CODA3.ppt Talk]
 +
** 1:00pm Tim [http://www.jlab.org/~whitey/Tim.pptx Talk]
 +
** 4:30pm Dave D and Alex S.
 +
 +
* Thursday 24th of April:
 +
** 10:00am Fernando [http://www.jlab.org/~barbosa/HallD_System_%20&_%20Infrastructure_%20Review.ppt Talk]
 +
** 1:00pm Cindy
 +
** 4:00pm Elliott [http://www.jlab.org/~wolin/Hall%20D%20Integration.pptx Talk]
 +
 +
* Tuesday, 29th of April
 +
** 4:00pm Rebecca
 +
 +
* Wednesday 30th of April Room A110:
 +
** 1:00 pm Fernando
 +
** 4:00 pm Dave D.
 +
 +
* Thursday 1st of May Room F326/327:
 +
** 1:00 pm Tim [http://www.jlab.org/~whitey/Tim1.pptx Talk]
 +
** 4:00 pm Elliott
 +
 +
* Friday 2nd of May Room F326/327:
 +
** 8:30 am Elke
 +
** 1:00 pm Graham
 +
** 2:30 pm Alex S.
 +
 +
* Monday 5th of May Room F326/327:
 +
** 9:00 am George
  
 
==Pre-Brief Materials==
 
==Pre-Brief Materials==
Line 55: Line 85:
 
Outlines:
 
Outlines:
  
* [[Overview Outline for May 2008]]
+
* [http://www.jlab.org/Hall-D/software/wiki/index.php/Electronics Electronics] information for May 2008 review
[http://www.jlab.org/Hall-D/software/wiki/index.php/Electronics Electronics] information for May 2008 review
+
 
* [[Trigger Outline for May 2008]]
 
* [[Trigger Outline for May 2008]]
 
* [[DAQ Outline for May 2008]]
 
* [[DAQ Outline for May 2008]]
 
* [[Online Integration Outline for May 2008]]
 
* [[Online Integration Outline for May 2008]]
*  Mechanical/integration/installation information
+
*  Mechanical/integration/installation [http://www.jlab.org/~whitey/May2008-pre-brief May 2008 prebrief]
 
+
Writeups:
+
  
  
 +
Documents:
 +
* L1 Trigger:  [https://halldweb.jlab.org/DocDB/0010/001038/001/HallD_Level_1_OverviewV3.doc GlueX-Doc-1038] (Dave Doughty)
 +
* CODA 3: [https://halldweb.jlab.org/DocDB/0010/001039/001/CODA%20Overview.doc GlueX-Doc-1039] (Graham Heyes)
 +
* Online integration:  [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=1036 GlueX-Doc-1036] (Elliott Wolin)
 +
* Level-1 Trigger Simulation: [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=1043 GlueX-doc-1043]  (Alex Somov)
 +
* Electronics Overview: [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=1040 GlueX-Doc-1040] (Fernando Barbosa)
  
 
==Presentations==
 
==Presentations==
Line 70: Line 103:
  
  
==Topics==
+
==Topics Under Review==
  
Below I list topics the review committee might focus on.  Clearly the committee cannot investigate all of these in depth, but we can expect they will want an overview of most of them, and may probe a few in depth.
+
Below I list topics the review committee might consider.  Clearly the committee cannot investigate all of these in depth, but we can expect they will want an overview of most of them, and may probe a few in depth.
  
  

Latest revision as of 12:39, 14 March 2017

Introduction

The May 2008 Hall D Subsystem Review will cover all aspects of Hall D that have not been reviewed previously under the auspices of the 12 GeV project office. This includes electronics, trigger, DAQ, event and hardware monitoring, experiment and hardware controls, and detector integration, assembly, and maintainability. Milestones for the electronics/trigger/DAQ/monitoring/controls part of the review can be found in Online Major Milestones.

Current planning is for a 1 1/2 day meeting the week of 7-May, with no parallel sessions. This will be a combined Hall D and Hall B review.

[| Review Website]

Charge for the Review Committee

Draft charge for the committee (see here for the latest):


The scope of this review includes the Hall D electronics and data acquisition systems, the mechanical assembly and installation of the various Hall D detector elements, and the general infrastructure for this new experimental Hall.

For the Hall D System and Infrastructure Design and Safety Review, you are asked to address the following questions:

  1. Are the technical performance requirements adequately defined for the systems under review? Are the plans for achieving technical performance and subsequent construction and testing sufficiently developed and documented for the present phase of the project?
  2. Are the plans to address recommendations of the recent Hall D detector system reviews sound and appropriately developed for this stage of the project?
  3. Are the current designs and plans likely to achieve the performance requirements with a low risk of cost increases, schedule delays, and technical problems?
  4. Are the element fabrication and assembly plans consistent with the overall project and Hall D schedule? Are the plans for the detector integration in the GlueX spectrometer and the associated Hall D infrastructure appropriately developed for the present phase of the project?
  5. Have ES&H considerations been adequately incorporated into the designs at their present stage?

Please address the above questions point-by-point. Note that several aspects of the Hall D detector, electronics, and data acquisition systems have been reviewed previously. Recent 2008 reviews include a February Hall D Forward Drift Chamber mini-review, a February Hall D calorimetry review, and a March Hall D Drift Chambers and associated Particle Identification systems review. You will be supplied with the reports from these earlier reviews along with additional pre-briefing materials.


Agenda

The current agenda can be found here.


Deadlines

  • Final presentations to Elke: 5-May close-of-business
  • Pre-brief material to reviewers: 30-April
  • Pre-brief material to Hall-D group to read: 23-April
  • Prebrief outlines: 11-April


Remote Connection to the Dry Runs

  • When in F326/327, ESNET will be available.
    • ESNET: 8542553
  • Otherwise, phone connections will be provided.
    • Dial +1-800-377-8846 : US
    • Dial +1-888-276-7715 : Canada
    • Dial +1-302-709-8424 : International
    • Enter participant code: 39527048# (remember the "#")

Dry Runs

All Dry runs are in F326/327

  • Wednesday 23rd of April:
    • 8:00am Graham Talk
    • 1:00pm Tim Talk
    • 4:30pm Dave D and Alex S.
  • Thursday 24th of April:
    • 10:00am Fernando Talk
    • 1:00pm Cindy
    • 4:00pm Elliott Talk
  • Tuesday, 29th of April
    • 4:00pm Rebecca
  • Wednesday 30th of April Room A110:
    • 1:00 pm Fernando
    • 4:00 pm Dave D.
  • Thursday 1st of May Room F326/327:
    • 1:00 pm Tim Talk
    • 4:00 pm Elliott
  • Friday 2nd of May Room F326/327:
    • 8:30 am Elke
    • 1:00 pm Graham
    • 2:30 pm Alex S.
  • Monday 5th of May Room F326/327:
    • 9:00 am George

Pre-Brief Materials

Outlines:


Documents:

Presentations

Topics Under Review

Below I list topics the review committee might consider. Clearly the committee cannot investigate all of these in depth, but we can expect they will want an overview of most of them, and may probe a few in depth.


Electronics

  • preamps
  • discriminators
  • F1TDC, FADC250, FADC125
  • timing distribution system
  • CTP, SSP, GTP
  • TI, TS, TF, TD
  • cable choices
  • HV systems
  • LV systems
  • C-W and other bases
  • SiPM's and other PMT's
  • crate and backplane choices (VXS, ATCA)
  • development and test strategies
  • etc.


Trigger

  • L1 algorithm
  • rates and backgrounds
  • crate sum + global sum strategy
  • overall trigger strategy
  • crate and hardware choices
  • trigger distribution system


DAQ

  • event size
  • data rate
  • computer hardware choices
  • network hardware choices and configuration
  • cpu and network utilization
  • software architecture
  • software components (ROC, EMU, ER, etc)
  • language choices
  • run control
  • farm architecture
  • event tranfer to silo
  • metadata recording


Event and Hardware Monitoring

  • event display
  • event monitoring system
  • alarm system
  • archive/display system


Experiment and Detector Controls

  • overall controls architecture (ECS/SCADA/DCS hierarchy)
  • DCS strategy (PLC usage, control loops, etc)
  • SCADA strategy (tentatively EPICS + perhaps MonAlisa)
  • ECS strategy (AFECS)
  • alarm system
  • archive/restore system
  • magnet and cryo control systems
  • interoperability with accelerator controls system
  • redundancy, failure modes, safety issues


Detector Integration

  • tolerances, keep-away zones
  • cable strategy and layout
  • crate layout
  • power, heat, cooling
  • grounding/shielding/EMC
  • mechanical drawing database
  • sign-off procedures


Detector Construction

  • strategy
  • assembly procedures
  • special tooling and equipment needed
  • personnel and equipment safety, other EH&S, etc.


Detector Maintenance

  • ease and expected frequency of access
  • access/disassembly/reassembly procedures
  • routine maintenance
  • expected component lifetimes
  • personnel and equipment safety, other EH&S, etc.