Difference between revisions of "March 13, 2013 Tracking CDC/FDC"
From GlueXWiki
(→Minutes) |
(→Minutes) |
||
Line 30: | Line 30: | ||
##We still need diagrams for the HV mounting blocks and some idea of the weight they would have to support. Lubomir and Beni will send these. | ##We still need diagrams for the HV mounting blocks and some idea of the weight they would have to support. Lubomir and Beni will send these. | ||
# Installation Details | # Installation Details | ||
− | ##Lubomir presented the latest installation schedule for the FDC. Some spikes in manpower (where not enough people were available or only a few people can be on the platform working on a task) had been spread out, resulting in the installation finishing several months later than previously thought (from November to January). | + | ##Lubomir presented the latest installation schedule for the FDC. Some spikes in manpower (where not enough people were available or only a few people can be on the platform working on a task) had been spread out, resulting in the installation finishing several months later than previously thought (from November to January). This gives considerably shortened time for CDC installation and commissioning; the no cost extension for the CDC work will need further extension. |
##We tried to identify tasks which might benefit from extra personnel. CMU's first-year grad students would be available in June/July. For each of the following, would extra people help to complete the task earlier? | ##We tried to identify tasks which might benefit from extra personnel. CMU's first-year grad students would be available in June/July. For each of the following, would extra people help to complete the task earlier? | ||
###BCAL installation | ###BCAL installation |
Revision as of 13:37, 13 March 2013
Meeting Time and Place
Wednesday March 13, 2013 at 11:00am At Jefferson Lab, the meeting will be held in F326
Connections
To connect from the outside, please use ESNET
- ) ESNET: 8542553
- )To connect by telephone, dial:
- You can look up toll-free number at http://www.readytalk.com/intl
- US and Canada: (866)740-1260 (toll free)
- International: (303)248-0285 (toll call)
- enter access code followed by the # sign: 3421244#
Hardware Agenda
- Announcement
- FDC Update
- CDC Update
- Installation Details
- FDC installation schedule 1 (last week), schedule 2 (this week)
Minutes
Present: Curtis, Naomi, Mark, Beni, Lubomir, Simon
- FDC Update
- CDC Update
- The gas mixer MFCs were exchanged for larger capacity models and the CDC now has 50/50 Ar/CO2 flowing through at 1100sccm (one chamber volume per day) and exhausting through 6 bubblers into a fume hood.
- Gary added another rubber support at each corner of the support rail.
- We are preparing to move the DAQ electronics in.
- We still need diagrams for the HV mounting blocks and some idea of the weight they would have to support. Lubomir and Beni will send these.
- Installation Details
- Lubomir presented the latest installation schedule for the FDC. Some spikes in manpower (where not enough people were available or only a few people can be on the platform working on a task) had been spread out, resulting in the installation finishing several months later than previously thought (from November to January). This gives considerably shortened time for CDC installation and commissioning; the no cost extension for the CDC work will need further extension.
- We tried to identify tasks which might benefit from extra personnel. CMU's first-year grad students would be available in June/July. For each of the following, would extra people help to complete the task earlier?
- BCAL installation
- labelling and bundling the FDC cables
- testing the HV and LV units
- cable tray installation
- When would the HV and LV crates be available?