* Discuss crystal module install, shimming etc... [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha
 
* Discuss crystal module install, shimming etc... [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha
 
* Cable update [[Media:FCAL2_lv,board.pdf]]
 
* Cable update [[Media:FCAL2_lv,board.pdf]]
 
== Minutes ==
 
* Discussed minutes from last meeting
 
** what inspections/marking/labeling are needed prior to removal of lead glass blocks?
 
*** Malte to come up with a written procedure of what they plan on
 
*** Need for good tracking of all modules
 
*** There will be several surveys and measurements for baseline
 
*** Sasha wants to minimize rewrapping - needs to come up with a threshold
 
*** Malte and Mark Dalton wish to be involved in FCAL module dis-assy
 
* Going through new version of Gant chart
 
** Matt commented on the fact that some dates do not make sense
 
** Need to update Gant chart with more realistic time frames
 
** Need to tie Sasha's manpower chart into Gant
 
** Malte making base stress test plan to determine weak base
 
*** to be done in January
 
*** prepare stock pile of new bases
 
* Discussed need for written procedures for all aspects of the project
 
** Sasha wishes to be responsible for all procedures pertaing to lead glass and crystal modules
 
** He may need some help? Who will do what - This needs to be decided in order for things to go smoothly
 
* Discussed desire to downgrade Hall for GERT only, can ESB be downgraded?
 
* Discussed the need for a planned quantity of modules to be re-wrapped
 
** This will be based on Sasha's proposed student manpower for 3 months
 
** 700 modules to be re-wrapped is the current baseline
 
** Sasha will obtain materials for many more just in case
 
* Discussed cables
 
** Sasha Fernando proposed a change to put PCBs at chains for LV
 
*** Proposed horizontal layout will be too crowded
 
*** Will meet in a separate meeting again to decide on this
 
* Sasha showed a working layout for tables and shelving in hall for lead glass and crystal modules
 
** Concern with stability of free standing shelving
 
** Can tie 2 shelves together for stability
 
** Modify existing wall shelving for length of lead glass modules
 
** Need to determine how much existing shelving and what is needed to procure
 
* Discussed rack and crate layout
 
** Sasha showed his proposed crate layout
 
** Need to strategically place racks for simplified cable paths
 
** Show 3d model of rack layout next meeting
 
* Discussed need for mock ups
 
** Maybe use ComCal as a mock up for new cabling in January when it is removed from the hall
 
** Use lead glass to verify all wrapping /rework procedure so traing can be done well for students
 
** Use videos to teach students?
 
* Discussed use of 2 scissor lifts instead of big platform upstream of the FCAL
 
** Need to demonstrate stability of lift at heights
 
** Rent 2nd larger lift with 4 ft extension ($1K / month)
 