Difference between revisions of "March 12, 2023, FCAL Insert Installation Meeting"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 6: Line 6:
 
== Agenda ==
 
== Agenda ==
 
* Minutes from last meeting  https://halldweb.jlab.org/wiki/index.php/March_5,_2023,_FCAL_Insert_Installation_Meeting
 
* Minutes from last meeting  https://halldweb.jlab.org/wiki/index.php/March_5,_2023,_FCAL_Insert_Installation_Meeting
* Go through updated Gant chart
+
* Go through updated Procedure
 
** [[Media:FCAL2_schedule_v2a.pdf]]
 
** [[Media:FCAL2_schedule_v2a.pdf]]
** What inspections/marking/labeling/testing needed prior to glass block removal?
 
** Surveys before removal
 
** Who is responsible for what?
 
 
* Discuss Lead Glass and crystal module removal/install [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha
 
* Discuss Lead Glass and crystal module removal/install [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha
* Manpower and task division [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha
 
 
* Cable update [[Media:FCAL2_lv,board.pdf]]
 
* Cable update [[Media:FCAL2_lv,board.pdf]]
* Monitoring system discussion
 
* Assembly in ESB
 
 
[[image:Both_step.jpeg|thumb]]
 
[[image:JBweld_cooling_test.jpeg|thumb]]
 
[[image:Glass_module_steps.jpeg|thumb]]
 
  
 
== Minutes ==
 
== Minutes ==

Revision as of 17:06, 11 April 2023

Meeting Time and Place

Wednesday March 12, 2023 9am At Jefferson Lab, Hall D Counting House and on Zoom

Agenda

Minutes

  • Discussed minutes from last meeting
    • what inspections/marking/labeling are needed prior to removal of lead glass blocks?
      • Malte to come up with a written procedure of what they plan on
      • Need for good tracking of all modules
      • There will be several surveys and measurements for baseline
      • Sasha wants to minimize rewrapping - needs to come up with a threshold
      • Malte and Mark Dalton wish to be involved in FCAL module dis-assy
  • Going through new version of Gant chart
    • Matt commented on the fact that some dates do not make sense
    • Need to update Gant chart with more realistic time frames
    • Need to tie Sasha's manpower chart into Gant
    • Malte making base stress test plan to determine weak base
      • to be done in January
      • prepare stock pile of new bases
  • Discussed need for written procedures for all aspects of the project
    • Sasha wishes to be responsible for all procedures pertaing to lead glass and crystal modules
    • He may need some help? Who will do what - This needs to be decided in order for things to go smoothly
  • Discussed desire to downgrade Hall for GERT only, can ESB be downgraded?
  • Discussed the need for a planned quantity of modules to be re-wrapped
    • This will be based on Sasha's proposed student manpower for 3 months
    • 700 modules to be re-wrapped is the current baseline
    • Sasha will obtain materials for many more just in case
  • Discussed cables
    • Sasha Fernando proposed a change to put PCBs at chains for LV
      • Proposed horizontal layout will be too crowded
      • Will meet in a separate meeting again to decide on this
  • Sasha showed a working layout for tables and shelving in hall for lead glass and crystal modules
    • Concern with stability of free standing shelving
    • Can tie 2 shelves together for stability
    • Modify existing wall shelving for length of lead glass modules
    • Need to determine how much existing shelving and what is needed to procure
  • Discussed rack and crate layout
    • Sasha showed his proposed crate layout
    • Need to strategically place racks for simplified cable paths
    • Show 3d model of rack layout next meeting
  • Discussed need for mock ups
    • Maybe use ComCal as a mock up for new cabling in January when it is removed from the hall
    • Use lead glass to verify all wrapping /rework procedure so traing can be done well for students
    • Use videos to teach students?
  • Discussed use of 2 scissor lifts instead of big platform upstream of the FCAL
    • Need to demonstrate stability of lift at heights
    • Rent 2nd larger lift with 4 ft extension ($1K / month)