Difference between revisions of "March 11, 2011 Fab Meeting"
From GlueXWiki
(→Action Items) |
|||
(12 intermediate revisions by the same user not shown) | |||
Line 12: | Line 12: | ||
* FDC construction update | * FDC construction update | ||
* Upcoming work | * Upcoming work | ||
+ | ** FDC practice foils, motion stage, Readiness review, lights | ||
+ | ** BCAL Wedges | ||
+ | ** Solenoid 3 | ||
+ | ** Solenoid 2 | ||
+ | ** Permanent magnets | ||
+ | ** Collimator cave - install stands | ||
+ | ** Platform - install this summer | ||
== Action Items== | == Action Items== | ||
− | + | * Permanent Magnet chambers reworked/leak check chambers | |
− | * Permanent Magnet chambers reworked/leak check | + | * Remove vacuum chamber and build/install new |
− | * | + | * Need to make sure access to BCAL wedges in ESB (Tom) |
+ | * Block up existing BCAL boxes | ||
+ | * Move coils 1 and 4 to Hall D | ||
+ | * Test flow switch in Mag field - Scot | ||
+ | * Tom to work with Jim F. for BCAL readout prototyoe | ||
+ | * Order remaining controls items for the remaining coils - Scot | ||
==Discussions== | ==Discussions== | ||
− | **In attendance C. Heck, D. Butler, A. Johnson, T. Carstens, Tim Whitlatch | + | **In attendance C. Heck, D. Butler, A. Johnson, T. Carstens, Tim Whitlatch, S. Speigel, D. Boyles, G. Humble, M. Beizer, B. Bunton, T. Mann, M. Stevens, |
+ | |||
+ | |||
+ | *Solenoid coil 4 test complete | ||
+ | *Coil 3 leak checking | ||
+ | * Coil 2 Inspections needed | ||
+ | * Double shift starts 21March |
Latest revision as of 09:52, 11 March 2011
Meeting Time and Place
Friday March 11, 2011 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231
Agenda
- ESH&Q minute - Tornado
- Announcements - Budget, Party
- training - ensure up to date
- Manpower
- Solenoid Test Status *
- FDC construction update
- Upcoming work
- FDC practice foils, motion stage, Readiness review, lights
- BCAL Wedges
- Solenoid 3
- Solenoid 2
- Permanent magnets
- Collimator cave - install stands
- Platform - install this summer
Action Items
- Permanent Magnet chambers reworked/leak check chambers
- Remove vacuum chamber and build/install new
- Need to make sure access to BCAL wedges in ESB (Tom)
- Block up existing BCAL boxes
- Move coils 1 and 4 to Hall D
- Test flow switch in Mag field - Scot
- Tom to work with Jim F. for BCAL readout prototyoe
- Order remaining controls items for the remaining coils - Scot
Discussions
- In attendance C. Heck, D. Butler, A. Johnson, T. Carstens, Tim Whitlatch, S. Speigel, D. Boyles, G. Humble, M. Beizer, B. Bunton, T. Mann, M. Stevens,
- Solenoid coil 4 test complete
- Coil 3 leak checking
- Coil 2 Inspections needed
- Double shift starts 21March