March 08 2023 Tech group meeting
From GlueXWiki
Revision as of 08:09, 8 March 2023 by Whitey (Talk | contribs) (Created page with "= Meeting Time and Place == Wednesday March 08, 2022 9:30am TED 2536 and Teams == Agenda == * Safety - ePAS ** All 16 gauge extension chords to be taken out of service - on...")
Meeting Time and Place =
Wednesday March 08, 2022 9:30am TED 2536 and Teams
Agenda
- Safety - ePAS
- All 16 gauge extension chords to be taken out of service - only by 12 gauge from now on
- Raises and Promotions - March 1
- FCAL2 current Tasks
- Schedule updated
- FCAL2 Design tidbits
- Monitoring panel discussion - waiting on Sasha
- Cabling/patch panels - Waiting on Sasha
- need cooling pipe to chiller assy
- need dark room mod for electronic patch panels, need to complete 0200 final assy dwg
- Rack platform
- need installation drawing
- outer plexiglass
- Tungsten - waiting on monitoring decision
- Insulation
- Man lifts - Scot renting one
- Liftable frame mods
- Cable trays
- drip pan
- FCAL2 Assembly
- Assemble FCAL2 step plates/cooling blocks - completed - will go with what we have and address during assy
- Epoxy fittings to Cooling Manifold
- Testing cooling plates
- Bend/solder copper tubes - complete
- HDList updates - weekly!
- Shims needed for assy
- KLONG dwgs
- On Call -