Line 33: | Line 33: | ||
#* Light sources in Bcal | #* Light sources in Bcal | ||
# FCAL | # FCAL | ||
− | # | + | ## Radiation Damage Studies. |
− | #* | + | ## Procurement Contract |
− | #* | + | ##* EVMS reporting and project schedule |
+ | ##* Scheduling the Readiness Review | ||
+ | ## Update on FEU-84-3 PMTs | ||
# BCAL | # BCAL | ||
− | # | + | ## Construction Status |
− | # | + | ## Fibre tests |
# BCAL Readout | # BCAL Readout | ||
− | # | + | ## Simulations |
− | # | + | ## SiPMs |
− | # | + | ## Light guides. See [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1432 GlueX-doc-1432] Figures 1,2,13,14. |
− | # | + | ## Geometry for guides, sensors, cooling and cables |
− | # | + | ## Update on USM MOU |
# Other business | # Other business | ||
Revision as of 11:33, 3 March 2010
Teleconference Time: 11:00 a.m. EST
- ESNET and EVO session
- Phone in CC F326 is 757-269-6337
- Phone in the Regina Videoconference Suite is 306-585-4204
- Phone only if requested:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 77438230# (remember the "#"). Phone line by request only.
Contents
Items for followup from previous meeting(s)
- Calibration/Monitoring
- Geometry for inputing monitoring sources into Bcal
- Fcal
- Specify the number of Rad Hard blocks to writeup a change request to the project.
- Investigate mechanical issues associated with supporting lead glass on top of shashlyk modules (Lubomir, Serguei). Will to send drawings of the modules.
- Bcal
- Specify the normalization and dynamic range for the number of photons/GeV in showers
- Decide on specific grouping for SiPM sums
- Possibility of using air gap for SiPM coupling
- Finalize shapes of "Winston guides"
- Simulations:
- List of energies and angles to be simulated for the purpose of establishing the dynamic range of light to the SiPMs.
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Calibration/Monitoring
- Light sources in Bcal
- FCAL
- Radiation Damage Studies.
- Procurement Contract
- EVMS reporting and project schedule
- Scheduling the Readiness Review
- Update on FEU-84-3 PMTs
- BCAL
- Construction Status
- Fibre tests
- BCAL Readout
- Simulations
- SiPMs
- Light guides. See GlueX-doc-1432 Figures 1,2,13,14.
- Geometry for guides, sensors, cooling and cables
- Update on USM MOU
- Other business
Minutes
Attendees: