− | ''Attending: | + | ''Attending: Beni, Elton, John, Eugene, Tim, Lubomir, Yi (JLab); Will, Serguei (USM); Matt (IU); Zisis, Andrei (UofR). |
+ | |||
+ | # Announcements | ||
+ | #* ''Starting this week, we will move the Bcal Readout meeting and Cal Working Group meetings to TUESDAY 11:00 | ||
+ | # Review of Action Items | ||
+ | # Calibration | ||
+ | # FCAL | ||
+ | ## Construction Status: mechanical, bases | ||
+ | ## Drawings for Fcal structure (Tim) | ||
+ | # BCAL | ||
+ | ## Construction Status: builds, fibre QA | ||
+ | ## First article testing (Yi) | ||
+ | # [http://www.jlab.org/~semenov/meeting110329.pdf Simulations] |
Revision as of 13:09, 29 March 2011
Teleconference Time: 11:00 a.m. EST
- ESNET (Number is 8542553) and EVO session (GlueX Calorimetry meeting room)
- JLab Phone: in CC F326 is 757-269-6337
- Regina Phone: in LB228 is 306-585-4204
- Athens Phone: in Christina's office is 011-30-210-727-6947
- Phone connection only upon request.
- +1-866-740-1260 : US+Canada
- +1-303-248-0285 : International
- then enter participant code: 3421244# (remember the "#").
- or www.readytalk.com (and code without the #)
Items for followup from previous meeting(s)
- Monitoring
- Fcal: check cross talk of calibration inputs across modules.
- Simulation
- Need to study the reconstruction efficiency.
- Andrei will send David instructions for using summing and configuration files.
Tentative Agenda
- Announcements
- Starting this week, we will move the Bcal Readout meeting and Cal Working Group meetings to TUESDAY 11:00
- Review of Action Items
- Calibration
- FCAL
- Construction Status: mechanical, bases
- Drawings for Fcal structure (Tim)
- BCAL
- Construction Status: builds, fibre QA
- First article testing (Yi)
- Simulations
Minutes
Attending: Beni, Elton, John, Eugene, Tim, Lubomir, Yi (JLab); Will, Serguei (USM); Matt (IU); Zisis, Andrei (UofR).
- Announcements
- Starting this week, we will move the Bcal Readout meeting and Cal Working Group meetings to TUESDAY 11:00
- Review of Action Items
- Calibration
- FCAL
- Construction Status: mechanical, bases
- Drawings for Fcal structure (Tim)
- BCAL
- Construction Status: builds, fibre QA
- First article testing (Yi)
- Simulations