1) Our schedule for the proposal (back in time):
 
1) Our schedule for the proposal (back in time):
 +
 
- We may expect that PAC will be scheduled for July.
 
- We may expect that PAC will be scheduled for July.
 +
 
- We have to submit our proposal 6 weeks in advance (May-June)
 
- We have to submit our proposal 6 weeks in advance (May-June)
 +
 
- It will probably take 4 weeks for the GlueX Collaboration to review (April-May)
 
- It will probably take 4 weeks for the GlueX Collaboration to review (April-May)
 +
 
- In March, we plan to ask Rolf for a technical review (upon the Jim Napolitano's suggestion)
 
- In March, we plan to ask Rolf for a technical review (upon the Jim Napolitano's suggestion)
 +
 
- GlueX Collab meeting is scheduled for Feb 16-18 and we have to talk about KL.
 
- GlueX Collab meeting is scheduled for Feb 16-18 and we have to talk about KL.
  

Revision as of 13:20, 29 November 2016

Meetings

We will use Blue Jeans for remote participation.

You can connect to the remote meeting via your browser: https://jlab.bluejeans.com/178535051/

Call-in Directions:

1. Dial: Primary Number: +1-408-740-7256 Toll free number: +1-888-240-2560

2. Enter meeting ID: 178535051

3. Press #

Meeting title: YSTAR2016

International phone numbers are listed on: http://bluejeans.com/numbers


The tentative agenda is

1) Our schedule for the proposal (back in time):

- We may expect that PAC will be scheduled for July.

- We have to submit our proposal 6 weeks in advance (May-June)

- It will probably take 4 weeks for the GlueX Collaboration to review (April-May)

- In March, we plan to ask Rolf for a technical review (upon the Jim Napolitano's suggestion)

- GlueX Collab meeting is scheduled for Feb 16-18 and we have to talk about KL.

2) We have to make a conceptual design of the KL project which allows to estimate a cost of the KL. To do that we have to draw a Note and then ask Eugene to ask Tim to make it.

3) Status of MC simulations of expected data.

ds/dO for KLp-->K+n (Mikhail)

ds/dO and Sigma for KLp-->K+Xi (Nick)

4) Status of neutron background simulations (Igor)

5) Schedule for the next meeting

6) etc