Line 22: | Line 22: | ||
** [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings Link to the earlier design meetings] | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings Link to the earlier design meetings] | ||
* Light Monitoring System -- Arshak | * Light Monitoring System -- Arshak | ||
+ | |||
+ | =Minutes= | ||
+ | |||
+ | * 25 CRYTUR crystals have be ordered (the PR signed) | ||
+ | * Continue wrapping CRYTUR crystals (Mindy) - 10 done during last week (35 crystals are available, expect to receive 50 more in November) | ||
+ | * Fabricated 10 more modules, the grand total is 1313 | ||
+ | * Meeting with the DSG group will be scheduled during next week. We'll discuss the group involvement in the project during FCAL2 installation phase. | ||
+ | * |
Revision as of 11:25, 28 October 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Moving JEF hardware reports to CALWG?
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Order 25 CRYTUR crystals (Total 1613 + 25 = 1638)
- Wrapped CRYTUR crystals: 727
- Available for wrapping: 762 - 727 = 25 (10 crystals were wrapped during last week)
- DSG group continues wrapping (Mindy)
- List of available parts
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 1313 (10 modules fabricated since last week)
- All SICCAS 576 SICCAS
- 737 CRYTUR, available: 25
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Light Monitoring System -- Arshak
Minutes
- 25 CRYTUR crystals have be ordered (the PR signed)
- Continue wrapping CRYTUR crystals (Mindy) - 10 done during last week (35 crystals are available, expect to receive 50 more in November)
- Fabricated 10 more modules, the grand total is 1313
- Meeting with the DSG group will be scheduled during next week. We'll discuss the group involvement in the project during FCAL2 installation phase.