Below we propose a design for fiber connections between the Rack Room and the Hall, and network switch and terminal server placement.
 
Below we propose a design for fiber connections between the Rack Room and the Hall, and network switch and terminal server placement.
 
::Elliott Wolin, Mark Dalton
 
::Elliott Wolin, Mark Dalton
::11-Oct-2013
+
::14-Oct-2013
  
  
Line 45: Line 45:
 
|US1 || 0 || 0 || 0 || 0 || 0 || none || 0 || 0 || 0 || Not sure what's going on here
 
|US1 || 0 || 0 || 0 || 0 || 0 || none || 0 || 0 || 0 || Not sure what's going on here
 
|-
 
|-
|U2A || 9 || 12 || 9 || 100 MB/s || 770 MB/s || 24 strand || 1 || 1 || 5 || comment
+
|U2A || 9 || 12 || 9 || 100 MB/s || 770 MB/s || 24 strand || 1 || 1 || 5 || 12 strands needed for 5 10**7
 
|-
 
|-
|U2B || 9 || 12 || 9 || 136 MB/s || 916 MB/s || 24 strand || 1 || 1 || 5 || comment
+
|U2B || 9 || 12 || 9 || 136 MB/s || 916 MB/s || 24 strand || 1 || 1 || 5 || 12 strands needed for 5 10**7
 
|-
 
|-
 
|D2A || 9 || 19 || 10 || < 80 MB/s || 370 MB/s || 12 strand || 2 || 1 || 0 || includes 2 gas shed connections
 
|D2A || 9 || 19 || 10 || < 80 MB/s || 370 MB/s || 12 strand || 2 || 1 || 0 || includes 2 gas shed connections

Revision as of 13:55, 14 October 2013

Below we propose a design for fiber connections between the Rack Room and the Hall, and network switch and terminal server placement.

Elliott Wolin, Mark Dalton
14-Oct-2013


Notes

  • Based on 10**8 photons/sec, 200 kHz trigger rate, existing L1 rejection algorithm, block=1 mode, no compression.
  • Ethernet port counts from Fernando's rack layouts and information from Dave Butler concerning other controls requirements.
  • We own about 15 24-port managed switches with 10 GBit/s fiber uplinks, some being used in EEL building and other places.
  • Switches can uplink 1.25 GBytes/sec.
  • 8-port managed switches with 1 GBit/s fiber uplinks exist.
  • Only managed switches (no hubs!) allowed in hall.
  • Fibers come in bundles of 12 or 24, 2 fibers needed for one uplink.
  • Standard JLab practice is to terminate all fibers in patch panel when bundles installed.
  • Bundle/patch panel installation is expensive, can run much cheaper patch fibers from switch in one rack area to patch panel in nearby rack area.
  • DAQ crates require two Ethernet connections each, one for the ROC and one for the fan tray.
  • Some ROC's are only used for control, not DAQ (e.g. BCAL LED Pulser).
  • ROC's each need an RS232 connection to a terminal server, terminal servers require an Ethernet connection.
  • Each terminal server has xxx ports.
  • Can run copper RS232 patch cable from one rack area to terminal server in nearby rack area.
  • Will eventually need direct fiber link to ROC if max bandwidth > 80 MB/s, assuming 10**8 photons/sec.



Hall Fiber Specifications
Rack DAQ Connections Controls Connections TS Connections Max Single ROC Bandwidth Total Uplink Bandwidth Fiber Bundle Switches Terminal Servers Possible ROC Fiber Uplinks Comment
T1 6 12 6 <80 MB/s 151 MB/s 12 strand 1 1 0 Comment
U1A 0 7 1 0 low none 1 0 0 Fiber patch to xxxx, TS patch to yyyy
U1B 5 8 5 <50 MB/s 93 MB/s 12 strand 1 1 0 comment
U1C 2 3 2 low low none 1 0 0 Fiber patch to xxx, TS patch to yyyy
U1D 0 1 0 0 0 none 0 0 0 Copper ethernet patch to xxxx.
N1 8 13 8 < 80 MB/s 450 MB/s 12 strand 1 1 0 comment
S1 8 13 8 < 80 MB/s 450 MB/s 12 strand 1 1 0 comment
US1 0 0 0 0 0 none 0 0 0 Not sure what's going on here
U2A 9 12 9 100 MB/s 770 MB/s 24 strand 1 1 5 12 strands needed for 5 10**7
U2B 9 12 9 136 MB/s 916 MB/s 24 strand 1 1 5 12 strands needed for 5 10**7
D2A 9 19 10 < 80 MB/s 370 MB/s 12 strand 2 1 0 includes 2 gas shed connections
D2B 6 7 6 < 80 Mb/s 300 MB/s 12 strand 1 0 0 TS patch to D2A
UN1 0 20 0 0 low none 1 0 0 Fiber patch to xxx