tof meeting minutes
 +
 +
elton, mark, beni
 +
paul sasha ian
 +
 +
calibration and alignment
 +
sasha going through materails, research
 +
sub committee
 +
 +
technical design report, updating in progress by Paul
 +
 +
no tests on the new light guides
 +
 +
independent support of curved metal that supports soft steel
 +
 +
cross bars on the end
 +
 +
prototype will be machined at FSU
 +
materials will be boutht by jlab
 +
 +
drawings will be shipped to FSU

Revision as of 08:24, 11 May 2012

Thursday, May 10, 2012
10:00 am EDT
JLab: CEBAF Center, F326/327

Agenda

  1. Announcements
  2. Review of last TOF bi-weekly meeting
  3. GlueX Collaboration Meeting Agenda
  4. Mechanical design: Tim, Chuck
  5. Prototype status: Paul, Sasha
  6. TDC choice: all
  7. Contract Status: Mark, Paul
  8. Calibration and Alignment
  9. Technical Design Report contribution

Communication

Videoconference

  1. ESNet: 8542553
  2. EVO: EVO site

Slides

Talks can be deposited in the directory /group/halld/www/halldweb1/html/talks/2012-2Q on the JLab CUE. This directory is accessible from the web at https://halldweb1.jlab.org/talks/2012-2Q/ .

Chairman's Cell Phone

(757)504-0664

Minutes

tof meeting minutes

elton, mark, beni paul sasha ian

calibration and alignment sasha going through materails, research sub committee

technical design report, updating in progress by Paul

no tests on the new light guides

independent support of curved metal that supports soft steel

cross bars on the end

prototype will be machined at FSU materials will be boutht by jlab

drawings will be shipped to FSU