* '''JLab''': Mark Ito (chair), Chris Keith, Sascha Somov, Simon Taylor, Beni Zihlmann
 
* '''JLab''': Mark Ito (chair), Chris Keith, Sascha Somov, Simon Taylor, Beni Zihlmann
  
paul contacted hamamatsu, factory confirms delivery schedule
+
==Review of minutes from the last meeting==
one base of each type, select and select mod, by 22 Aug
+
remainder on sep 27
+
  
chair has signed the mou and moved it to the dean
+
We went over [[GlueX PID Meeting, July 23, 2010#Minutes|the minutes from the July 23 meeting]].
  
wed. bad for Paul
+
* '''PMT purchase'''. Paul contacted Hamamatsu. The factory confirms the following delivery schedule:
 +
*# One base of each type ("select" and "select mod") by August 22.
 +
*# Remainder of order (3 more of each type) by September 27.
 +
* '''FSU MOU''': Paul's chair has signed the MOU and it has been sent to the Dean.
 +
* '''Splitter discussion'''. We have not met to discuss this yet. Paul's recollection was that Fernando Barbosa will make a prototype passive splitter and send it to Paul for testing.
  
he was going to get a splitter from fernando
+
==TOF prototype work==
  
prototype Paul?
+
Paul gave a report.
  
JLab china gluex talk
+
* '''New trigger scheme'''. Sasha O. has started work on the new trigger scheme to read-out tagged ADC and TDC data.
 
+
* '''Purchasing wrapping material'''. Paul looked into buying more of the ESR material reported on at the last meeting. The official name of the product is DF2000MA and is made by 3M. The company is reluctant to sell it in large rolls, but their standard sizes are too small for our purposes. Paul is exploring the possibility of rough cut sheets, with a dimensions approximately those which we want to use.
sasha away
+
* '''Lab space at FSU'''. Paul told us he is getting another new lab in the Nuclear Research Building for assembly, enough room to set up stations for the various tasks.
 
+
working on the new trigger processor, readout tagged adc and tdc events together.
+
 
+
material from 3M, current name DF2000MA, was told that we
+
rough cut sheets a possibility
+
 
+
MOU issues:
+
• lab space, getting another new lab in nuclear research building for assembly, enough room to set up stations
+

Revision as of 12:55, 9 August 2010

Location, Time

Friday, August 6, 2010
2:00 pm EDT
JLab: CEBAF Center, Room F326/7
ESNet: 8542553
EVO: direct meeting link
Conference Group: 800-377-8846, participant code: 77438230
Slides: talks can be deposited in the directory /group/halld/www/halldweb1/html/talks/2010-08 on the JLab CUE (you have to be a member of the "halld" group). This directory is accessible from the web at https://halldweb1.jlab.org/talks/2010-08/ .

Agenda

  1. Announcements
  2. Minutes from the last meeting
  3. Time-of-Flight
    1. Prototype progress
    2. Status of the MOU
  4. Start Counter
    1. prototype status
  5. Target
    1. Status of the MOU
  6. Action Items

Minutes

  • FSU: Paul Eugenio
  • JLab: Mark Ito (chair), Chris Keith, Sascha Somov, Simon Taylor, Beni Zihlmann

Review of minutes from the last meeting

We went over the minutes from the July 23 meeting.

  • PMT purchase. Paul contacted Hamamatsu. The factory confirms the following delivery schedule:
    1. One base of each type ("select" and "select mod") by August 22.
    2. Remainder of order (3 more of each type) by September 27.
  • FSU MOU: Paul's chair has signed the MOU and it has been sent to the Dean.
  • Splitter discussion. We have not met to discuss this yet. Paul's recollection was that Fernando Barbosa will make a prototype passive splitter and send it to Paul for testing.

TOF prototype work

Paul gave a report.

  • New trigger scheme. Sasha O. has started work on the new trigger scheme to read-out tagged ADC and TDC data.
  • Purchasing wrapping material. Paul looked into buying more of the ESR material reported on at the last meeting. The official name of the product is DF2000MA and is made by 3M. The company is reluctant to sell it in large rolls, but their standard sizes are too small for our purposes. Paul is exploring the possibility of rough cut sheets, with a dimensions approximately those which we want to use.
  • Lab space at FSU. Paul told us he is getting another new lab in the Nuclear Research Building for assembly, enough room to set up stations for the various tasks.