(Created page with "== Meeting Time and Place == Monday, February 12, 2024, 1pm Hall D Counting House * Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Pavel Degtiarenko, Tim W...")
 
(Agenda)
Line 6: Line 6:
 
== Agenda ==
 
== Agenda ==
  
* Review minutes from last meeting  
+
* Review minutes from last meeting https://halldweb.jlab.org/wiki/index.php/January_16,_2024_KLONG_CPS_Design_Meeting
 
* Review new basic 3D model and compare to Pavel's model (Pavel, Keith)
 
* Review new basic 3D model and compare to Pavel's model (Pavel, Keith)
 
** Pavel Presentation [[media:Conceptual Design of CPS Eng.Mtg. 01-16-24.pdf]]
 
 
* Magnet update (Josh)
 
* Magnet update (Josh)
* Develop path forward for final design (meetings/schedule etc...) (all)
+
* Discuss path forward (Tim/all)
  
 
== Minutes ==
 
== Minutes ==

Revision as of 16:48, 7 February 2024

Meeting Time and Place

Monday, February 12, 2024, 1pm Hall D Counting House

  • Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Pavel Degtiarenko, Tim Whitlatch, Eugene Chudakov, Josh Ballard

Agenda

Minutes

  • Discussed background of the project and the goal of getting the design completed in a little over a year
  • Pavel presented the current conceptual design based on his analysis
    • Copper radiator
      • Operate remotely
      • 300 micron repeatability
      • 2 thicknesses plus blank
      • 2cm diameter?
      • rad hard materials (no encoder)
      • maybe proximity switch/LVDT for positions
    • Need to develop a complete thermal model as design progresses
    • Use of a steel core for support
    • overall alignment of magnet and radiator to be within a few hundred microns
    • Ability to move the assembly (with out magnets) completely out of the beam to the north wall
    • Ability to crane or forklift the core out during decommissioning
    • Total weight approximately 90 tonnes
    • Need temperature sensors on copper, lead and steel
    • Need to fine tune the thermal calcs on copper absorber
    • Need water temperature and flow meters
    • US magnet to be designed to 2x current plus 10%
    • Need tungsten block to absorb the electron beam on magnet failure
    • Consult with Hall C folks on their design experience of a CPS
    • Josh fine tuning the magnet design
      • Moving coils 12cm from beamline
      • maybe less steel

Action Items

  • Pavel to check into exporting his model in a compatible format for NX ( Open Scad etc...
  • Stephanie to look into importable files from her end
  • Tim to provide stp file of copper absorber from ANSYS for Designers (complete)
  • Tim to setup bi-weekly meetings
  • Tim to set up and Engineer/Designer detailed meeting