Controls Meeting 21-Mar-2013

From GlueXWiki
Revision as of 13:27, 22 March 2013 by Wolin (Talk | contribs)

Jump to: navigation, search

Agenda

  • Announcements
  • Minutes from previous meeting 7-Mar-2013
  • Requirements for BCAL/FCAL LED pulser calibration system - Elton
  • Update on FCAL dark room - Dan, John, Manuel
  • Update on PLC test stand - Dave
  • Counting House status - Hovanes, Elliott
    • furniture, computers, networks, etc.
  • EPICS update - Hovanes
  • Solenoid update - Mark, Scot, Elliott
  • Progress on other controls applications - Dave
    • storing/retrieving PLC parameters
  • What is the role of the JInventory system - All
    • relation to DAQ, HV/LV control, cabling?
    • need to finalize conventions and get all equipment entered
    • need to purchase/print and install barcode labels
    • some software improvements and bug fixes remain
    • other halls interested, may provide programming manpower
  • Mantis task tracker
    • start using this again?
  • Midas elog


  • Experiment Control Supervisor - Elliott


Time/Location

9:30AM Thurs 21-Mar-2013 CC A110


Announcements

Next Meeting

9:30am Thurs 4-Apr-2013


Minutes

Present: Elliott W, Elton S, Dan B, Fernando B, John L, Yi Q, Scot S, Mark S, Dave B, Tara B, Alex S, Hovanes E.


BCAL/FCAL Pulser

Elton gave a thorough overview of the LED pulser calibration system:

  • System needs to send trigger to TS and TTL pulses to LED flashers.
  • External power includes 5V and bias to set LED intensity, will use SiPM power supplies.
  • LED flashed via capacitor discharge.
  • Will have LED boards, distribution boards and external TTL pulsing system.
  • LED boards done, distribution boards and pulsing system to be designed.
  • For trigger timing all cables will be equal length, will get ~5ns jitter.
  • Need 50' LEMO cables from VME crates to distribution cards.
  • Cables from distribution boards about 12'.
  • 4 lines go to each LED board.
  • Will use three CAEN V1495 modules to generate TTL pulses, about $5k each incl. mezzanine boards.
  • Max 16 TTL channels per V1495.
  • Will likely use two VME crates, one for BCAL with two V1495's, one for FCAL with one V1495.
  • Not clear if crates need to be purchased, hope to find free slots in other crates.
  • Hope to not have to put V1495's in DAQ crates (discriminator crates are ok).
  • V1495 has many LVDS outputs suitable for input to TS.
  • FCAL has 10 LED boards per quadrant, 4 LED's per board, three colors.
  • FCAL does not use distribution board, TTL signals go directly to LED boards.
  • Ben will program V1495, 2 man-weeks allocated.
  • Need to program pulse width, trig-to-pulse delay, start, stop, #pulses, etc.
  • Once written and tested the FPGA code is not expected to need to change.
  • V1495 has programmable switches that could be used to implement local operational modes.
  • Will use EPICS to control V1495 operation.
  • EPICS driver needs to be written (Nerses or Hovanes).
  • Considering running pulsers all the time at low rate during data taking.
  • Max conceivable pulse rate 1 MHz, less ok.


FCAL Controls

John and Dan reported:

  • Dark room parts list to be sent out, want feedback from JLab techs on choices.
  • If no comments received will choose parts themselves.
  • Dark room might be done in 2-3 months.
  • One working power supply here, remainder in production or repair.
  • Will soon have enough equipment to test FCAL in manual mode.


Counting House

  • Rack room is ready and working, some computer and network equipment will be ordered in May.
  • Furniture ordered, should arrive in a few weeks.
  • Some conference equipment not ordered yet.
  • Chairs finally ordered.


PLC Test Stand

  • Parts coming.
  • Need to test EPICS connection to CompactLogix processor (SNS swears it works).
  • Dave will create tags, Hovanes will try to access them via EPICS IOC.


EPICS

  • Beni and Hovanes working on auto-configuring power supply drivers.
  • Nerses may finally be coming in May!


Solenoid