Coil Test Weekly Meeting 23-Sep-2010
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 23-Sep-2010 9:30am ARC 428
Agenda
- DOE review 28-Sep - George, Elliott
- final status for Glenn's talk
- preparation for visit to Test Lab by reviewers
- Conduct of Operations - Josh, Elliott
- results of Wed meeting
- OSP documents and review - Elliott, George
- what is left to do?
- when can/must we turn everything in?
- Installation status
- what's left?
- when do we give two weeks notice to Errol?
- Test plan - Josh
- addition of check valve and relief valve in lead flow system
- Magnet power supply and interlock commissioning - Cody
- latest status
- Controls racks - Scot
- strain gauge interlock
- UPS interlock
- anything else?
- PLC programming/testing status - Mark W
- UPS interlock
- guard shack
- what's left?
- backup PLC programmer?
- tutorial?
- EPICS <--> PLC communications - Wesley
- PV list from Jonathan Creel
- under what circumstances do we notify the guard shack?
- HMI and EWEB programming - Yi, Hovanes
- Josh's screens
- current status
- tutorial?
- Coil repair status - George
- Solenoid review 25-26 Oct
- Preparations for testing next coil - George, Elliott
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring