Line 11: Line 11:
 
* DOE review 28-Sep - George, Elliott
 
* DOE review 28-Sep - George, Elliott
 
** final status for Glenn's talk
 
** final status for Glenn's talk
 +
** preparation for visit to Test Lab by reviewers
 
* Conduct of Operations - Josh, Elliott
 
* Conduct of Operations - Josh, Elliott
 
** results of Wed meeting
 
** results of Wed meeting
Line 20: Line 21:
 
** when do we give two weeks notice to Errol?
 
** when do we give two weeks notice to Errol?
 
* Test plan - Josh
 
* Test plan - Josh
 +
** addition of check valve and relief valve in lead flow system
 
* Magnet power supply and interlock commissioning - Cody
 
* Magnet power supply and interlock commissioning - Cody
 
** latest status
 
** latest status
Line 40: Line 42:
 
** tutorial?
 
** tutorial?
 
* Coil repair status - George
 
* Coil repair status - George
 +
* Solenoid review 25-26 Oct
 
* Preparations for testing next coil - George, Elliott
 
* Preparations for testing next coil - George, Elliott
 
** update P&I
 
** update P&I

Revision as of 16:59, 20 September 2010

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 23-Sep-2010 9:30am ARC 428


Agenda

  • DOE review 28-Sep - George, Elliott
    • final status for Glenn's talk
    • preparation for visit to Test Lab by reviewers
  • Conduct of Operations - Josh, Elliott
    • results of Wed meeting
  • OSP documents and review - Elliott, George
    • what is left to do?
    • when can/must we turn everything in?
  • Installation status
    • what's left?
    • when do we give two weeks notice to Errol?
  • Test plan - Josh
    • addition of check valve and relief valve in lead flow system
  • Magnet power supply and interlock commissioning - Cody
    • latest status
  • Controls racks - Scot
    • strain gauge interlock
    • UPS interlock
    • anything else?
  • PLC programming/testing status - Mark W
    • UPS interlock
    • guard shack
    • what's left?
    • backup PLC programmer?
    • tutorial?
  • EPICS <--> PLC communications - Wesley
    • PV list from Jonathan Creel
    • under what circumstances do we notify the guard shack?
  • HMI and EWEB programming - Yi, Hovanes
    • Josh's screens
    • current status
    • tutorial?
  • Coil repair status - George
  • Solenoid review 25-26 Oct
  • Preparations for testing next coil - George, Elliott
    • update P&I
    • splices
    • yoke location
    • piping adaptors
    • downstream yoke spacers
    • controls racks rewiring