Coil Test Weekly Meeting 11-Nov-2010
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 4-Nov-2010 9:30 am ARC 428
Agenda
- Long term personnel outlook - Elliott
- Experience with control system - All
- what have we learned, and is it written down?
- what will we do different for the next coil?
- what needs to be added/modified/improved?
- EWEB strip charts
- Preparation for powered operations - Elliott
- OSP, checklists, etc.
- shunt installation/wiring, connection to interlock/control system
- ground fault detection
- fast DAQ, which channels, what rates?
- rewire quench detector
- Hall probe
- pickup coils
- 240 V UPS on Danfysik control boards, main breaker
- more redundancy?
- interlock checkout
- ODH on platform?
- broken/flaky sensors/gauges/instruments
- replace Pt sensor in heat exchanger with Si diode?
- C-glass calibrations?
- vacuum valve interlock
- what to do about strain gauges?
- PI Responsibilities during test - Jonathan
- Low power magnet testing 5A, 50A,100A - Elliott
- High power magnet testing 100-1500A - Elliott
- Identify possible turn to turn shorts during ramping - Eugene
- Assess Heim column centering in coil - George
- Assess Axial column forces - George
- Estimate LN2 and He heat leak - Jonathan
- Assess LN2 and LHe thermal siphons - Jonathan
- Controls racks - Scot
- strain gauge and UPS interlocks
- PLC operations - Mark W
- PID tuning, calibration, JT valve limits, etc.
- magnet ramp down mechanism
- UPS interlock
- another tutorial
- EPICS - Hovanes
- connection to guard shack and notification conditions
- pager status and strategy
- HMI and EWEB programming - Yi, Hovanes
- program access to archived data
- another tutorial
- Coil repair status - George
- Learn how to use Linux for web and email - Elliott
- Solenoid review 7-Dec
- Purchase of another PLC and Ethernet module - Elliott
- Hall D Technical web page
- Preparations for testing next coil - George, Scot, Elliott
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring
- quench detector connections
- connectors on next coil
- fix known problems
- what else?