Preliminary Run Plan
Activity Duration (PAC Days) Current Target Collimator Radiator Comment
Full target (Production) 20 27 nA Pb (0.3 mm) 3.4 mm style="text-align:left" |
Empty Target 1.5? 27 nA Pb (0.3 mm) 3.4 mm style="text-align:left" | Run at higher current?
Diamond Alignment 0.5? 100 nA? Pb (0.3 mm) 3.4 mm JD70-103 / JD70-107 |style="text-align:left" |
Trigger Commissioning 1? 100 nA? Pb (0.3 mm) 3.4 mm style="text-align:left" |
Beam Energy Calibration 0.5? 100 nA Pb (0.3 mm) 3.4 mm style="text-align:left" | Collimator Blocking for 5 min, periodically
TAC Runs 1.5? 27 Pb (0.3 mm) 3.4 mm style="text-align:left" |