Preliminary Run Plan
Activity Duration (PAC Days) Current Target Collimator Radiator Comment
Full target (Production) 20 27 Pb (0.3 mm) 3.4 JD70-103 / JD70-107
Empty Target 1.5? 27 Pb (0.3 mm) 3.4 JD70-103 / JD70-107
Diamond Alignment 0.5? 27 Pb (0.3 mm) 3.4 JD70-103 / JD70-107
Trigger Commissioning 1? 27 Pb (0.3 mm) 3.4 JD70-103 / JD70-107
Beam Energy Calibration 0.5? 100 Pb (0.3 mm) 3.4 JD70-103 / JD70-107 Collimator Blocking, 5 min, periodically
TAC Runs 1.5? 27 Pb (0.3 mm) 3.4 JD70-103 / JD70-107