Difference between revisions of "CDC travel plans"
From GlueXWiki
Line 1: | Line 1: | ||
− | Overview | + | <h3>Overview</h3> |
#Load up at CMU - looking at Oct 28-30 or Nov 4-6 | #Load up at CMU - looking at Oct 28-30 or Nov 4-6 | ||
#Ideally, store truck indoors overnight | #Ideally, store truck indoors overnight | ||
Line 6: | Line 6: | ||
##Arrival after ? pm - go to Hall D, drive in, CDC in truck overnight, drive to EEL the next day and unload | ##Arrival after ? pm - go to Hall D, drive in, CDC in truck overnight, drive to EEL the next day and unload | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | Preparations | + | <h3>Preparations</h3> |
#Add reinforcements to CDC cart for forklift | #Add reinforcements to CDC cart for forklift | ||
##Order materials for reinforcements | ##Order materials for reinforcements | ||
− | ##Calculate position of CDC's CM | + | ##Calculate position of CDC's CM - Naomi - approx 20" from Al plate, will revise |
#Swap straight wheels for swivel wheels | #Swap straight wheels for swivel wheels | ||
##Order swivel wheels | ##Order swivel wheels | ||
Line 32: | Line 27: | ||
− | + | <h3>Equipment for readout</h3> | |
− | + | ||
− | Equipment for readout | + | |
#4 long scint paddles are to travel down from CMU | #4 long scint paddles are to travel down from CMU | ||
#Do we need to bring any NIM modules? | #Do we need to bring any NIM modules? | ||
− | Shopping list | + | <h3>Longer term plans - after arrival at JLab</h3> |
+ | #CDC is to be stored in EEL 126? until FDC installation is complete | ||
+ | #HV blocks need to be added | ||
+ | #CDC mini-readout in EEL can be set up once FDC has moved into Hall D | ||
+ | #Expect CDC installation to be in Jan 2014 (engineering) or Dec 2013 (electronics) [[September_27,_2013_Installation | schedules are linked to installation meeting Sept 27]] | ||
+ | |||
+ | |||
+ | <h3>Shopping list<h3> | ||
#Unistrut & fittings to modify cart | #Unistrut & fittings to modify cart | ||
#Swivel wheels | #Swivel wheels |
Revision as of 11:01, 8 October 2013
Contents
Overview
- Load up at CMU - looking at Oct 28-30 or Nov 4-6
- Ideally, store truck indoors overnight
- Drive to JLab
- Arrival before ?pm - go to EEL to unload
- Arrival after ? pm - go to Hall D, drive in, CDC in truck overnight, drive to EEL the next day and unload
Preparations
- Add reinforcements to CDC cart for forklift
- Order materials for reinforcements
- Calculate position of CDC's CM - Naomi - approx 20" from Al plate, will revise
- Swap straight wheels for swivel wheels
- Order swivel wheels
- Find filters to cap CDC gas tubes
- Wrap CDC in bubblewrap
- Order bubble-wrap
- Cut dual-density foam to size
- Locate mooring snubbers
- Rent a truck
- Need to measure temp near CDC - buy long thermocouple?
- Update packing list - extra things to bring (HVBs, manifold etc) installation doc with packing list
- Book accommodation at resfac
- Find somewhere to keep truck indoors overnight at CMU - Naomi
- Negotiate loading bay access - Curtis
- Arrange time with fork lift driver - Gary
Equipment for readout
- 4 long scint paddles are to travel down from CMU
- Do we need to bring any NIM modules?
Longer term plans - after arrival at JLab
- CDC is to be stored in EEL 126? until FDC installation is complete
- HV blocks need to be added
- CDC mini-readout in EEL can be set up once FDC has moved into Hall D
- Expect CDC installation to be in Jan 2014 (engineering) or Dec 2013 (electronics) schedules are linked to installation meeting Sept 27