Difference between revisions of "Beam Commissioning Plan"

From GlueXWiki
Jump to: navigation, search
(Assumptions)
m (Text replacement - "hdops.jlab.org/wiki" to "halldweb.jlab.org/hdops/wiki")
 
(13 intermediate revisions by 2 users not shown)
Line 1: Line 1:
'''Draft Outline for Commissioning'''
+
[https://halldweb.jlab.org/hdops/wiki/index.php/Fall_2014_Commissioning_Plan Hall D Official Fall 2014 Commissioning Plan]
  
=Review Sequence=
+
[[Preparations for Internal Photon Beam Commissioning]]
# Electron beam
+
#* OSP and small internal review in order to power and map tagger magnet
+
#* Transfer of tagger magnet operation to accelerator, so that it can be reviewed as part of  ARR II (nominally Jan)
+
# Photon beam
+
#* Review of photon beamline (radiator to photon beam dump). Nominally scheduled for March, at least 3 months prior to beam delivery
+
#* Items to be covered by this review include:
+
#*# tagger hodoscope
+
#*# tagger microscope
+
#*# profile monitor -- <u>where does this go? (not considered by Photon Beam WG so far)</u>
+
#*# active collimator
+
#*# halo monitors
+
#*# other photon beam monitors -- <u>pair spectrometer? total absorption counter?</u>
+
# Experimental Equipment Hall D
+
#*  Experimental apparatus in Hall D (prior to use with beam)
+
  
= Equipment List=
+
[[Draft Outline for Commissioning]]
[http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=2363 Commissioning Bullets] GlueX-doc-2363
+
 
+
=Electron beam=
+
==Goals==
+
#  Safely deliver electron beam to the electron beam dump <ref name="TN08033"> Abkemeier, E. et al., "Shielding Basis for hall D Complex," July 2008, JLAB-TN-08-033  </ref>
+
 
+
==Assumptions==
+
# Accelerator has qualified the machine protection system (MPS) and the personnel safety system (PSS) for the tagger building
+
# Assume steel blocks (> 20" thick) are stacked in front of <u>the entrance to</u> the photon beam pipe to the <u>tagger</u> hall to prevent any direct beam spray from traveling down to Hall D.
+
 
+
==Checklist at low current I~1uA, [[tune mode]] <ref name=TN07022> Freyberger, A. and Tiefenback, M., "Diagnostic Specifications for the 12 Gev Upgrade," 2007, JLAB-TN-07-022  </ref> ==
+
# Check beam is centered on the beam dump
+
# Scan position of beam over the area of the radiator
+
# Check single rates at various positions in the tagger enclosure (electronic racks)
+
# Check single rates at the location of the tagger microscope
+
# Check single rates at the location of the tagger broad band hodoscope
+
# Verify tagger magnet excitation curve matches predictions, e.g. for different beam energies
+
# Verify controls for all beamline elements work as expected
+
# Check radiation levels in the tagger hall <ref name="TN08033"/>
+
<ol start="9">
+
<li> Establish location in the hall for electronic racks safe from radiation </li>
+
<li> Identify sources of background (scraping) in the hall. </li>
+
<li> Check Fast Shutdown system </li>
+
</ol>
+
 
+
==Checklist at low current I < 100 nA?, CW==
+
# Verify proper operation of beam as in pulsed mode
+
# Check single rates at various positions in the tagger enclosure (electronic racks)
+
# Check single rates at the location of the tagger microscope
+
# Check single rates at the location of the tagger broad band hodoscope
+
# Identify sources of background (scraping) in the hall.
+
# Check out amorphous ladder controls
+
# Commission halo pmts located on the electron beam pipe to the dump (i.e. adjust HV settings)
+
# Change radiators and check relative thicknesses using halo pmts
+
# Use accelerator harp to determine beam centroid and width
+
# Use amorphous ladder harp to verify beam centroid, width and halo
+
 
+
==Checklist at high current I > <u>2 &mu;A</u>, CW==
+
# Verify proper operation of beam as in low current situation
+
# Check single rates at various positions in the tagger enclosure (electronic racks)
+
# Check single rates at the location of the tagger microscope
+
# Check single rates at the location of the tagger broad band hodoscope
+
# Check radiation levels in the tagger hall
+
# Check radiation levels in Hall D
+
# Check radiation levels in the tagger service building
+
 
+
==Abnormal conditions==
+
 
+
# High radiation levels in any or all areas of interest
+
# Accidental loss of power to vertical bend string
+
# Accidental loss of power of tagger magnet
+
# Accidental loss of vacuum
+
# <u>Accidental motion of goniometer target frame into beam</u>
+
 
+
=Photon beam=
+
==Goals==
+
# Determine characteristics of photon beam in Hall D
+
#  Safely deliver photon beam through the hall to the photon beam dump
+
 
+
==Assumptions==
+
# Accelerator has qualified the machine protection system (MPS) and the personnel safety system (PSS) for Hall D and the counting house
+
# Delivery of electron beam through tagger to electron dump has been accomplished
+
# Operation is assumed CW, but perhaps one should start with pulsed mode
+
# Amorphous radiator installed with 10<sup>-5</sup> <u>radiation lengths</u> thickness, typical
+
# Steel blocking photon beam pipe in tagger hall has been removed
+
# Initially the solenoidal magnet is off
+
 
+
==Notes==
+
# We should identify all apertures along the beam line to be aware of possible locations for scraping
+
 
+
==Checklist, current I< 100 nA==
+
 
+
==Location: before active collimator==
+
# Require profile monitor to be installed and operational
+
# Require active collimator to be installed and operational
+
# Require halo monitors 1 to be installed and operational upstream of cave wall
+
# Check that detector elements in Hall D are off and prepared
+
# Check profile of photon beam exiting the beam pipe into cave
+
# Determine center of photon beam relative to photon beamline
+
# Compare with response of active collimator
+
# Use this exercise to calibrate active collimator response
+
# Scan the electron beam over the face of the radiator to establish aperture and check that photon beam profile behaves as expected
+
# Check feedback signals of active collimator to control system. (Once understood, these can be used in real time to correct the beam position on the collimator).
+
# Study the stability of the beam with and without feedback from the active collimator
+
# Equalize rates in halo counters located in front of the cave back wall
+
# Check radiation levels inside the collimator cave
+
# Establish possible locations for electronics
+
# Check radiation levels in Hall D
+
# Check radiation levels in the counting house.
+
# Determine suitability of delivering beam into the hall before proceeding.
+
 
+
==Location: exiting pair spectrometer==
+
# Commission the ladder with the PS converter including the harp
+
# Require halo monitors 2 to be installed and operational downstream of the PS
+
# Perform a harp scan using the converter ladder
+
# Measure intensity and energy distribution of photon beam using pair spectrometer fine and coarse arrays.
+
# Determine rate sensitivity to movements of the electron beam on the radiator
+
# Check radiation levels inside the collimator cave
+
# Check radiation levels inside Hall D
+
# Measure single rates of detectors  (e.g. BCAL, FCAL, TOF)
+
 
+
==Location: behind FCAL==
+
 
+
# Relocate profile monitor behind the FCAL?
+
# Verify expected profile (projection of collimator) through the detector
+
# Verify expected photon beam rate
+
# Check radiation levels inside Hall D
+
# Measure single rates of detectors  (e.g. BCAL, FCAL, TOF)
+
 
+
==Alignment of beam to target==
+
# Install commissioning target and start counter
+
# Check that photon beam is transmitted cleanly through target cell
+
# Use start counter rates to verify the photon beam is centered on the target
+
# Check singles rates of detectors  (e.g. BCAL, FCAL, TOF)
+
 
+
=References=
+
<references />
+

Latest revision as of 23:31, 31 March 2015

Hall D Official Fall 2014 Commissioning Plan

Preparations for Internal Photon Beam Commissioning

Draft Outline for Commissioning