Difference between revisions of "BLTWG Meeting 04/04/2011"
From GlueXWiki
(→Agenda) |
|||
(3 intermediate revisions by 2 users not shown) | |||
Line 2: | Line 2: | ||
* Place: ESNET and EVO (with telephone bridge id 317 3697) | * Place: ESNET and EVO (with telephone bridge id 317 3697) | ||
* Connecting: instructions are [[Tagged Beam Group Biweekly Meetings|here]] | * Connecting: instructions are [[Tagged Beam Group Biweekly Meetings|here]] | ||
− | * Present: | + | * Present: Sascha S., Yi Q., Hovanes E., Igor S., Richard J., Curtis M. |
===Agenda=== | ===Agenda=== | ||
Line 11: | Line 11: | ||
#* summary of accomplishments | #* summary of accomplishments | ||
#* experience with data acquisition, limiting factors | #* experience with data acquisition, limiting factors | ||
− | #* experience with the trigger counters, limiting factors | + | #* [https://www.jlab.org/~somov/micro experience with the trigger counters, limiting factors ] |
#* experience with the active collimator | #* experience with the active collimator | ||
#* plans for data analysis | #* plans for data analysis | ||
Line 18: | Line 18: | ||
# Response so far on tagger magnet bid -- ''Tim'' | # Response so far on tagger magnet bid -- ''Tim'' | ||
# Early procurement items for tagger microscope construction -- ''Richard'' | # Early procurement items for tagger microscope construction -- ''Richard'' | ||
− | # New diamond thinning proposal for SBIR Phase II with Sinmat -- Richard | + | # New diamond thinning proposal for SBIR Phase II with Sinmat -- ''Richard'' |
+ | # Updates on design of the Pair Spectrometer -- ''Sascha'' |
Latest revision as of 12:20, 4 April 2011
- Time: 11:00 EST
- Place: ESNET and EVO (with telephone bridge id 317 3697)
- Connecting: instructions are here
- Present: Sascha S., Yi Q., Hovanes E., Igor S., Richard J., Curtis M.
Agenda
- Review recent beam tests in Hall B -- discussion
- online logbook for microscope prototype tests
- online logbook for active collimator tests
- summary of accomplishments
- experience with data acquisition, limiting factors
- experience with the trigger counters, limiting factors
- experience with the active collimator
- plans for data analysis
- prospects for further beam in Hall B, in case problems show up in the analysis
- Progress on tagger vacuum box design -- Tim
- Response so far on tagger magnet bid -- Tim
- Early procurement items for tagger microscope construction -- Richard
- New diamond thinning proposal for SBIR Phase II with Sinmat -- Richard
- Updates on design of the Pair Spectrometer -- Sascha